4510 1/4-1/2 S 9TH AVE 90043
Certificate Information: 4510 1/4-1/2 S 9TH AVE 90043
- Application / Permit
- 22010-20000-04520
- Plan Check / Job No.
- B22VN13593
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 41'-8.5" x 39'-0" DUPLEX ACCESSORY DWELLING UNITS, PER CA GOT. CODE 65852.2(e)(1)(D) AND LAMC 12.22 A.33 (c)-(d), (g).
- Permit Issued
- Issued on 1/31/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2022 | LUIS RINCON |
| Corrections Issued | 9/13/2022 | LUIS RINCON |
| Building Plans Picked Up | 9/20/2022 | APPLICANT |
| Plan Check Approved | 1/12/2023 | LUISANGEL VALENZUELA |
| Issued | 1/31/2023 | APPLICANT |
| CofO in Progress | 6/6/2024 | ANTHONY EGSON |
| Permit Finaled | 6/10/2024 | DEROLD HAUFF |
| CofO Issued | 6/10/2024 | DEROLD HAUFF |
| Permit Finaled | 6/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 10/24/2022 | STEVE MELGAR |
| Construction near power lines | Cleared | 11/21/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/30/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 1/10/2023 | STEVE MELGAR |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/28/2023 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/5/2023 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 9/9/2023 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/2/2023 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2023 | Approved | ANTHONY EGSON |
| Green Building Rough | 10/6/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 10/6/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 12/29/2023 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 1/2/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 1/2/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/4/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 1/5/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2024 | Approved | ANTHONY EGSON |
| Green Building Rough | 1/5/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/19/2024 | Approved | ANTHONY EGSON |
| Insulation | 1/24/2024 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 1/30/2024 | Partial Approval | ANTHONY EGSON |
| Drywall Nailing | 2/9/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 5/3/2024 | Approved | ANTHONY EGSON |
| Final | 5/3/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/3/2024 | Approved | ANTHONY EGSON |
| Green Building Final | 5/3/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 5/3/2024 | Partial Inspection | JOSH MEISTER |
| PLUMBING-Final | 5/3/2024 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 5/3/2024 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 5/3/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 5/3/2024 | Approved | ANTHONY EGSON |
| Final | 5/10/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 5/10/2024 | Approved | ANTHONY EGSON |
| Service/Power Release | 5/10/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 5/30/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Service/Power Release | 5/30/2024 | Approved | ANTHONY EGSON |
| Final | 6/6/2024 | OK to Issue CofO | ANTHONY EGSON |