15918 W ECCLES ST 91343

Certificate Information: 15918 W ECCLES ST 91343

Application / Permit
22010-20000-04509
Plan Check / Job No.
B22VN13565
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW CONSTRUCTION 28'-0" X 46'-0" ADU PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/23/2024
Issuing Office
Current Status
CofO Issued on 1/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/27/2022 APPLICANT
Assigned to Plan Check Engineer 10/3/2022 LUISANGEL VALENZUELA
Corrections Issued 10/4/2022 LUISANGEL VALENZUELA
Applicant returned to address corrections 6/21/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 6/26/2023 DANIEL ABRAMYAN
Plan Check Approved 12/5/2023 DANIEL ABRAMYAN
No Progress 1/5/2024 LUISANGEL VALENZUELA
Plan Check Approved 1/5/2024 LUISANGEL VALENZUELA
Issued 2/23/2024 APPLICANT
CofO in Progress 1/2/2026 GAREN HAYRAPETYAN
Permit Finaled 1/9/2026 RUBEN SALAS
Permit Finaled 1/9/2026 RUBEN SALAS
CofO Issued 1/9/2026 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development Cleared 4/11/2023 SARAH YOUSSEF
Address approval Cleared 4/26/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/26/2023 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/26/2023 LEE GUILBEAUX
Sewer availability Cleared 4/26/2023 LEE GUILBEAUX
Construction near power lines Cleared 11/18/2023 RIDWAN HARDY
Construction within easement Cleared 11/18/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Ebrahimi,, Amirhosin; Lic. No.: C92049 8619 RESEDA BLVD UNIT 304B      NORTHRIDGE, CA 91324

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/23/2024 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 7/31/2024 Approved RAUL OLAGI
Wood Frame 12/3/2024 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 12/5/2024 Corrections Issued SALVADOR MARTINEZ
Wood Frame 12/11/2024 Partial Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 3/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 3/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/21/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 3/21/2025 Approved GAREN HAYRAPETYAN
Shower Pan 3/21/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 4/2/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 4/15/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 4/15/2025 Approved GAREN HAYRAPETYAN
Wood Frame 4/15/2025 Approved GAREN HAYRAPETYAN
Insulation 4/18/2025 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 4/18/2025 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 4/25/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 4/25/2025 Approved GAREN HAYRAPETYAN
Sewer 5/22/2025 Approved RYAN SALAZAR
Underground Mechanical 5/22/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/23/2025 Not Ready for Inspection SALVADOR MARTINEZ
Sewer 5/23/2025 Partial Inspection SALVADOR MARTINEZ
Interior/Exterior Lathing 6/6/2025 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 12/8/2025 Approved GAREN HAYRAPETYAN
Final 12/8/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 12/8/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 12/8/2025 SGSOV Approved GAREN HAYRAPETYAN
Service/Power Release 12/8/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Smoke Detectors 12/8/2025 Approved GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 12/8/2025 Approved GAREN HAYRAPETYAN
Final 1/2/2026 OK to Issue CofO GAREN HAYRAPETYAN
Service/Power Release 1/2/2026 Approved GAREN HAYRAPETYAN