15918 W ECCLES ST 91343
Certificate Information: 15918 W ECCLES ST 91343
- Application / Permit
- 22010-20000-04509
- Plan Check / Job No.
- B22VN13565
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW CONSTRUCTION 28'-0" X 46'-0" ADU PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/23/2024
- Issuing Office
- Current Status
- CofO Issued on 1/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 10/4/2022 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 6/21/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 6/26/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 12/5/2023 | DANIEL ABRAMYAN |
| No Progress | 1/5/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 1/5/2024 | LUISANGEL VALENZUELA |
| Issued | 2/23/2024 | APPLICANT |
| CofO in Progress | 1/2/2026 | GAREN HAYRAPETYAN |
| Permit Finaled | 1/9/2026 | RUBEN SALAS |
| Permit Finaled | 1/9/2026 | RUBEN SALAS |
| CofO Issued | 1/9/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development | Cleared | 4/11/2023 | SARAH YOUSSEF |
| Address approval | Cleared | 4/26/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2023 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 4/26/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/26/2023 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 11/18/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/18/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ebrahimi,, Amirhosin; Lic. No.: C92049 | 8619 RESEDA BLVD UNIT 304B NORTHRIDGE, CA 91324 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/23/2024 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 7/31/2024 | Approved | RAUL OLAGI |
| Wood Frame | 12/3/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Wood Frame | 12/11/2024 | Partial Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 3/20/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 3/20/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 3/21/2025 | Approved | GAREN HAYRAPETYAN |
| Shower Pan | 3/21/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 4/2/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 4/15/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 4/15/2025 | Approved | GAREN HAYRAPETYAN |
| Wood Frame | 4/15/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 4/18/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/18/2025 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 4/25/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 4/25/2025 | Approved | GAREN HAYRAPETYAN |
| Sewer | 5/22/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 5/22/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/23/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Sewer | 5/23/2025 | Partial Inspection | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 6/6/2025 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 12/8/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 12/8/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 12/8/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 12/8/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 12/8/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 12/8/2025 | Approved | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 12/8/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 1/2/2026 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Service/Power Release | 1/2/2026 | Approved | GAREN HAYRAPETYAN |