14619 W VALERIO ST 91405
Certificate Information: 14619 W VALERIO ST 91405
- Application / Permit
- 22010-20000-04504
- Plan Check / Job No.
- B22VN13554
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 860 SF accessory dwelling unit PER ORDINANCE
- Permit Issued
- Issued on 3/21/2023
- Issuing Office
- Current Status
- CofO Issued on 7/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | JAD BASMA |
| Corrections Issued | 10/9/2022 | JAD BASMA |
| Quality Review Completed | 10/19/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 1/4/2023 | JAD BASMA |
| Issued | 3/21/2023 | APPLICANT |
| CofO in Progress | 7/18/2025 | KEVIN BERBERYAN |
| Permit Finaled | 7/25/2025 | RUBEN SALAS |
| CofO Issued | 7/25/2025 | RUBEN SALAS |
| Permit Finaled | 7/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/21/2022 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 1/3/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 1/3/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Oasys Building Technology Inc; Lic. No.: 1086576-B | , |
| Engineer | Fischer,, Kurt; Lic. No.: NA5432 | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/17/2023 | Conditional Approval | MICHAEL SMITH |
| Pre-Inspection | 6/2/2023 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 7/27/2023 | Partial Approval | DAVID MATSON |
| PLUMBING-Rough | 7/27/2023 | Partial Approval | DAVID MATSON |
| Footing/Foundation/Slab | 9/5/2023 | Corrections Issued | RAUL OLAGI |
| Deputy Reinf. Concrete | 9/6/2023 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 9/12/2023 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 9/12/2023 | Corrections Issued | GREGG CUMMINGS |
| Deputy Reinf. Concrete | 9/25/2023 | Conditional Approval | DAVID MATSON |
| Deputy Drilled-In Anchors | 10/5/2023 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 12/28/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 12/29/2023 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/16/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 2/16/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 2/16/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 2/16/2024 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 2/16/2024 | Approved | CHRISTOPHER ROJAS |
| Wood Frame | 2/16/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 9/3/2024 | Corrections Issued | VINCENT HANLEY |
| Gas Test | 9/5/2024 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 9/5/2024 | Approved | VINCENT HANLEY |
| Sewer | 10/22/2024 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 10/22/2024 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 10/24/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/16/2025 | Approved | VINCENT HANLEY |
| Shower Pan | 5/16/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 6/20/2025 | Corrections Issued | VINCENT HANLEY |
| Final | 6/20/2025 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 6/20/2025 | Approved | VINCENT HANLEY |
| Green Building Final | 6/20/2025 | Approved | VINCENT HANLEY |
| HVAC-Final | 6/20/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 6/20/2025 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/20/2025 | SGSOV Not Ready | VINCENT HANLEY |
| Service/Power Release | 6/20/2025 | Approved | VINCENT HANLEY |
| Smoke Detectors | 6/20/2025 | Approved | VINCENT HANLEY |
| Final | 7/17/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 7/17/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Service/Power Release | 7/17/2025 | Partial Approval | KEVIN BERBERYAN |