6957 N WYSTONE AVE 91335
Certificate Information: 6957 N WYSTONE AVE 91335
- Application / Permit
- 22010-20000-04480
- Plan Check / Job No.
- B22VN13501
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 40'-0" x 30'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/29/2025
- Issuing Office
- Valley
- Current Status
- Issued on 5/29/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2022 | JEFFREY TANGONAN |
| Corrections Issued | 9/10/2022 | JEFFREY TANGONAN |
| Building Plans Picked Up | 9/12/2022 | APPLICANT |
| Applicant returned to address corrections | 10/13/2022 | JESSE ARELLANO |
| Plan Check Approved | 10/24/2022 | ALFRED RAMIREZ |
| Issued | 5/29/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/12/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 9/13/2022 | COLIN LOREDO |
| ZI | Cleared | 9/13/2022 | DANG NGUYEN |
| Low Impact Development | Cleared | 10/3/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 10/4/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chatsky,, German; Lic. No.: C84153 | 3876 HUNTERS GROVE CT MOORPARK, CA 93021 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/9/2025 | Approved | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 1/20/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 1/20/2026 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 1/20/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 1/20/2026 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 1/20/2026 | Approved | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 1/20/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 1/22/2026 | Conditional Approval | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 1/22/2026 | Partial Approval | ARUTYUN MADATYAN |
| Insulation | 1/23/2026 | Approved | DAVID FASTIGGI |
| Drywall Nailing | 1/28/2026 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 1/28/2026 | Approved | ARUTYUN MADATYAN |
| Shower Pan | 1/28/2026 | Approved | ARUTYUN MADATYAN |