20005 W RINALDI ST 91326

Certificate Information: 20005 W RINALDI ST 91326

Application / Permit
22010-20000-04461
Plan Check / Job No.
B22VN13462
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
EPLAN ***PROPOSED CORE & SHELL RESTAURANT FOR 3 TENANT SPACES "S8 BUILDING" PER CPC-2016-837-SP-MCUP-DRB-SPP-SPR
Permit Issued
Issued on 4/26/2023
Issuing Office
Current Status
CofO Issued on 5/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2022 APPLICANT
Assigned to Plan Check Engineer 9/8/2022 SINA KHOSRAVI
Corrections Issued 9/13/2022 SINA KHOSRAVI
Quality Review Completed 9/19/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 11/17/2022 SINA KHOSRAVI
Applicant returned to address corrections 12/1/2022 SINA KHOSRAVI
Applicant returned to address corrections 2/1/2023 SINA KHOSRAVI
Plan Check Approved 4/20/2023 SINA KHOSRAVI
Issued 4/26/2023 APPLICANT
CofO in Progress 5/28/2024 GREGORY POMISH
Permit Finaled 5/29/2024 RICKEY JACKSON
Permit Finaled 5/29/2024 RICKEY JACKSON
CofO Issued 5/29/2024 RICKEY JACKSON

Permit Application Clearance Information

Specific Plan Cleared 9/21/2022 SHEILA AHORAIAN
"D" conditions Cleared 9/28/2022 BRENNEN OBETO
"T" removal Cleared 9/28/2022 BRENNEN OBETO
Specific Plan Cleared 9/28/2022 BRENNEN OBETO
ZA Case Cleared 9/28/2022 BRENNEN OBETO
ZA Case Cleared 9/28/2022 BRENNEN OBETO
ZA Case Cleared 9/28/2022 BRENNEN OBETO
ZA Case Cleared 9/28/2022 BRENNEN OBETO
ZA Case Cleared 9/28/2022 BRENNEN OBETO
ZA Case Cleared 9/28/2022 BRENNEN OBETO
ZA Case Cleared 9/28/2022 BRENNEN OBETO
Address approval Cleared 9/29/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/12/2022 COLIN LOREDO
Sewer availability Cleared 10/12/2022 COLIN LOREDO
CPC Cleared 10/17/2022 DANG NGUYEN
Low Impact Development Cleared 10/19/2022 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/20/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 10/25/2022 KIRK LINKLATER
Green Code Cleared 11/4/2022 DONALD CRICHLOW
Highway dedication Cleared 11/8/2022 COLIN LOREDO
Hydrant and Access approval Cleared 11/29/2022 KURT CORRAL
DAS Clearance Cleared 1/30/2023 Joe Vo
Miscellaneous Cleared 2/13/2023 DANG NGUYEN
Fire Marshal Fire Life Safety Cleared 3/29/2023 ANDREW KO
GPI Written Notices Cleared 4/20/2023 SINA KHOSRAVI

Contact Information

Architect Rose,, Hugh Mason; Lic. No.: NA30461       ,
Contractor Moorefield Construction Inc; Lic. No.: 397892-B       ,
Engineer Schroeder,, Mark; Lic. No.: NA4110       ,

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/30/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 6/20/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 6/21/2023 Not Ready for Inspection JEFFREY FULTON
Footing/Foundation/Slab 6/26/2023 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 6/28/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 6/29/2023 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 7/14/2023 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 7/25/2023 Partial Inspection DANNY RODRIGUEZ
Deputy Wood Construction 8/2/2023 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/2/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/11/2023 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 8/16/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/23/2023 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/24/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 8/24/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 8/24/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 8/24/2023 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 9/6/2023 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 9/8/2023 Partial Inspection JEFFREY FULTON
Wood Frame 9/12/2023 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 9/19/2023 Partial Inspection DANNY RODRIGUEZ
Green Building Rough 10/4/2023 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 10/4/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 10/4/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 10/4/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 10/6/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 10/10/2023 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 10/10/2023 Conditional Approval JEFFREY FULTON
Green Building Rough 10/10/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 10/10/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 10/10/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 10/10/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 10/11/2023 Conditional Approval JEFFREY FULTON
Green Building Rough 10/13/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 10/13/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 10/13/2023 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 10/17/2023 Conditional Approval JEFFREY FULTON
Green Building Rough 10/25/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 10/25/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 10/25/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 10/26/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 11/13/2023 Partial Inspection JEFFREY FULTON
Structural Steel Frame 11/15/2023 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 12/4/2023 Not Ready for Inspection JEFFREY FULTON
Pre-Inspection 12/5/2023 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 12/28/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 12/28/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 12/28/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 12/28/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 12/29/2023 Conditional Approval JEFFREY FULTON
Interior/Exterior Lathing 2/7/2024 Partial Inspection JEFFREY FULTON
Final 5/2/2024 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 5/2/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 5/2/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 5/2/2024 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 5/2/2024 SGSOV Approved DANNY RODRIGUEZ
Smoke Detectors 5/2/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/2/2024 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 5/2/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/16/2024 Not Ready for Inspection GREGORY POMISH
Final 5/24/2024 OK to Issue CofO GREGORY POMISH
Footing/Foundation/Slab 5/24/2024 Approved GREGORY POMISH
Green Building Final 5/24/2024 Approved GREGORY POMISH
Green Building Rough 5/24/2024 Approved GREGORY POMISH
Smoke Detectors 5/24/2024 Approved GREGORY POMISH
Verify Sprinkler Sign Off 5/24/2024 Approved GREGORY POMISH
Wood Frame 5/24/2024 Approved GREGORY POMISH