10558 N ENCINO AVE 91344
Certificate Information: 10558 N ENCINO AVE 91344
- Application / Permit
- 22010-20000-04451
- Plan Check / Job No.
- B22VN13446
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU at rear of lot per state law
- Permit Issued
- Issued on 2/19/2024
- Issuing Office
- Current Status
- CofO Issued on 1/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2022 | MINA HABILI |
| Corrections Issued | 11/27/2022 | MINA HABILI |
| Applicant returned to address corrections | 5/11/2023 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 8/1/2023 | LUKE GONZALES |
| Applicant returned to address corrections | 10/4/2023 | MINA HABILI |
| Applicant returned to address corrections | 10/17/2023 | MINA HABILI |
| Applicant returned to address corrections | 10/20/2023 | MINA HABILI |
| Applicant returned to address corrections | 10/31/2023 | DANIEL SMILEY |
| Plan Check Approved | 11/2/2023 | JOE VO |
| Issued | 2/19/2024 | APPLICANT |
| CofO in Progress | 1/7/2026 | CHRISTOPHER ROJAS |
| Permit Finaled | 1/10/2026 | RUBEN SALAS |
| CofO Issued | 1/10/2026 | RUBEN SALAS |
| Permit Finaled | 1/10/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/17/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 2/1/2023 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 3/23/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 3/30/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | E - 1 Construction Inc; Lic. No.: 696414-B | , |
| Engineer | Nazarians,, Harmick; Lic. No.: C91232 | 9825 OSO AVE CHATSWORTH, CA 91311 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/4/2024 | Partial Approval | JAVIER RAMOS JR |
| Pre-Inspection | 4/4/2024 | Approved | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 4/15/2024 | Partial Inspection | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 4/15/2024 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2024 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 5/22/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/26/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 7/26/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 7/26/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/11/2024 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 9/11/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 9/11/2024 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/11/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/11/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 9/11/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 9/18/2024 | Partial Approval | MATTHEW NELSON |
| Drywall Nailing | 9/27/2024 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 9/27/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 10/15/2024 | Approved | MICHAEL CORTEZ |
| Final | 2/5/2025 | Corrections Issued | JAVIER RAMOS JR |
| Pre-Inspection | 2/5/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/27/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 6/27/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Final | 6/27/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 6/27/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| HVAC-Final | 6/27/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 6/27/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| Service/Power Release | 6/27/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 6/27/2025 | Approved | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 6/27/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 7/10/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 7/10/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 7/10/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 7/10/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 7/10/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/10/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 7/10/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 7/15/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 7/15/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 7/15/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 7/15/2025 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/15/2025 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 7/15/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 1/7/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Service/Power Release | 1/7/2026 | Approved | CHRISTOPHER ROJAS |