9760 N TELFAIR AVE 91331
Certificate Information: 9760 N TELFAIR AVE 91331
- Application / Permit
- 22010-20000-04426
- Plan Check / Job No.
- B22VN13385
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU WITH CARPORT PER ORDINANCE (2-STORY)
- Permit Issued
- Issued on 4/13/2023
- Issuing Office
- Current Status
- CofO Issued on 5/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | CARLOS MONTES |
| Corrections Issued | 11/12/2022 | CARLOS MONTES |
| Quality Review Completed | 11/15/2022 | GARO TELMI |
| Plan Check Approved | 4/13/2023 | CARLOS MONTES |
| Issued | 4/13/2023 | APPLICANT |
| CofO in Progress | 5/9/2025 | MICHEL ABAJAN |
| Permit Finaled | 5/15/2025 | RUBEN SALAS |
| CofO Issued | 5/15/2025 | RUBEN SALAS |
| Permit Finaled | 5/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/15/2022 | RYAN KIM |
| Clean Up Green Up | Cleared | 12/16/2022 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2022 | RYAN KIM |
| Sewer availability | Cleared | 12/19/2022 | RYAN KIM |
| Low Impact Development | Cleared | 1/18/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 1/20/2023 | RYAN KIM |
| Construction near power lines | Cleared | 3/1/2023 | RIDWAN HARDY |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: NA23963 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/27/2023 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Rough | 7/3/2023 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/11/2023 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2023 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/11/2023 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 8/11/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 8/11/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 8/11/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 8/11/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/17/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 8/17/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 8/17/2023 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 8/17/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2023 | Partial Approval | MICHEL ABAJAN |
| HVAC-Rough | 8/31/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Shower Pan | 8/31/2023 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 9/20/2023 | Approved | MICHEL ABAJAN |
| Shower Pan | 10/24/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/22/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 11/22/2023 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 11/22/2023 | Approved | MICHEL ABAJAN |
| Insulation | 12/4/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/4/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 12/11/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 8/22/2024 | Approved | MATTHEW NELSON |
| HVAC-Final | 10/11/2024 | Approved | MICHEL ABAJAN |
| Final | 11/25/2024 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 11/25/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 11/25/2024 | SGSOV Not Required | MICHEL ABAJAN |
| Service/Power Release | 11/25/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 11/25/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/28/2025 | Approved | MICHEL ABAJAN |
| Final | 4/28/2025 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Final | 4/28/2025 | Approved | MICHEL ABAJAN |
| Service/Power Release | 4/28/2025 | Corrections Issued | MICHEL ABAJAN |
| Final | 5/7/2025 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 5/7/2025 | Approved | MICHEL ABAJAN |