1461 1/2 E 56TH ST 90011

Certificate Information: 1461 1/2 E 56TH ST 90011

Application / Permit
22010-20000-04374
Plan Check / Job No.
B22VN13291
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 2-STORY (20'-0"x20'-0"), 800 SQFT ADU PER LAMC 12.22 A.33(c)(d)
Permit Issued
Issued on 5/12/2025
Issuing Office
Valley
Current Status
Issued on 5/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/31/2022 APPLICANT
Assigned to Plan Check Engineer 9/15/2022 PETER MOSESIAN
Corrections Issued 9/20/2022 PETER MOSESIAN
Quality Review Completed 9/27/2022 OMID HEDAYAT
Building Plans Picked Up 9/28/2022 APPLICANT
Applicant returned to address corrections 2/18/2025 ALFRED RAMIREZ
Plan Check Approved 4/30/2025 ALFRED RAMIREZ
Issued 5/12/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/17/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 11/2/2022 CELINA MORENO
Sewer availability Cleared 11/2/2022 CELINA MORENO
Hydrant and Access approval Cleared 11/19/2022 JOHN CONNEALLY
Construction near power lines Cleared 1/10/2023 RIDWAN HARDY
Community Plan Implem. Overlay Cleared 2/6/2023 ADALBERTO VERA
Community Plan Implem. Overlay Cleared 2/23/2023 JIMMY VIVAR
Community Plan Implem. Overlay Cleared 4/24/2023 JEANIE LAM
Roof/Waste drainage to street Cleared 1/16/2025 JEANIE LAM
Community Plan Implem. Overlay Cleared 3/27/2025 ANACANY HURTADO
Hold Cleared 10/2/2025 ALEXIS SCHULTZ

Contact Information

Contractor Espino Roberto; Lic. No.: 924261-B 10917 BENFIELD AVE      DOWNEY, CA 90241
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/3/2025 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 10/3/2025 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 11/4/2025 Corrections Issued JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 12/29/2025 Approved LUIS CASTRO
Footing/Foundation/Slab 12/29/2025 Corrections Issued LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 1/27/2026 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/1/2026 Corrections Issued LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 4/3/2026 Approved LUIS CASTRO
ELECTRICAL-Rough 4/15/2026 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 4/15/2026 Corrections Issued ALEJANDRO DE ARTOLA