17318 W TRIBUNE ST 91344
Certificate Information: 17318 W TRIBUNE ST 91344
- Application / Permit
- 22010-20000-04368
- Plan Check / Job No.
- B22VN11677
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 23' X 51' REC ROOM. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/4/2024
- Issuing Office
- Current Status
- CofO Issued on 4/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | RAPHAEL ROSAS |
| Corrections Issued | 8/31/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 9/1/2022 | STEVEN KIM |
| Applicant returned to address corrections | 8/30/2023 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/11/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 12/28/2023 | RAPHAEL ROSAS |
| Issued | 1/4/2024 | APPLICANT |
| CofO in Progress | 9/30/2025 | STEVEN BACK |
| Permit Finaled | 4/4/2026 | MICHAEL PELHAM |
| CofO Issued | 4/4/2026 | MICHAEL PELHAM |
| Permit Finaled | 4/4/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/26/2023 | OSCAR CASTRO |
| Low Impact Development | Cleared | 12/4/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 12/4/2023 | BRYAN GODINEZ |
| Sewer availability | Cleared | 12/4/2023 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2023 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 1819 SUNSHINE COURT GLENDALE, CA 91208 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/10/2024 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 7/9/2024 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2024 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 10/7/2024 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 10/11/2024 | Partial Approval | JEFFREY HARTLINE |
| PLUMBING-Rough | 1/8/2025 | Corrections Issued | STEVEN BACK |
| Sewer | 1/8/2025 | Approved | STEVEN BACK |
| PLUMBING-Rough | 1/17/2025 | Approved | STEVEN BACK |
| Pre-Inspection | 1/17/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Rough | 1/27/2025 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 3/3/2025 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 3/3/2025 | Approved | STEVEN BACK |
| Insulation | 3/3/2025 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 3/21/2025 | Approved | STEVEN BACK |
| Insulation | 3/21/2025 | Approved | STEVEN BACK |
| Shower Pan | 3/21/2025 | Approved | STEVEN BACK |
| Drywall Nailing | 3/28/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 3/28/2025 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 8/18/2025 | Approved | STEVEN BACK |
| Final | 8/18/2025 | Corrections Issued | STEVEN BACK |
| Green Building Final | 8/18/2025 | Approved | STEVEN BACK |
| HVAC-Final | 8/18/2025 | Approved | STEVEN BACK |
| PLUMBING-Final | 8/18/2025 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 8/18/2025 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 8/18/2025 | Approved | STEVEN BACK |
| Final | 8/19/2025 | Not Ready for Inspection | STEVEN BACK |
| Final | 9/30/2025 | OK to Issue CofO | STEVEN BACK |