10445 N PINYON AVE 91042

Certificate Information: 10445 N PINYON AVE 91042

Application / Permit
22010-20000-04350
Plan Check / Job No.
B22VN13200
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 31'10"X22'0" 1-STORY ACCESSORY DWELLING UNIT PER GC 66323 (NFPA 13 D FIRE SPRINKLERS REQUIRED THROUGHOUT)
Permit Issued
Issued on 8/29/2025
Issuing Office
Valley
Current Status
Issued on 8/29/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/30/2022 APPLICANT
Assigned to Plan Check Engineer 9/15/2022 MARVEL DELACRUZ
Corrections Issued 9/21/2022 MARVEL DELACRUZ
Quality Review Completed 9/23/2022 OMID HEDAYAT
Building Plans Picked Up 10/6/2022 APPLICANT
Applicant returned to address corrections 8/30/2023 MARVEL DELACRUZ
Applicant returned to address corrections 9/1/2023 MARVEL DELACRUZ
Applicant returned to address corrections 9/15/2023 MARVEL DELACRUZ
Plan Check Approved 9/19/2023 MARVEL DELACRUZ
No Progress 4/17/2025 MARVEL DELACRUZ
Plan Check Approved 8/27/2025 MARVEL DELACRUZ
Issued 8/29/2025 APPLICANT

Permit Application Clearance Information

Permit Cleared 2/3/2023 MARKOS PEREZ-BRAN
Miscellaneous Cleared 2/9/2023 DANG NGUYEN
Miscellaneous Cleared 2/9/2023 DANG NGUYEN
ZA Case Cleared 2/9/2023 DANG NGUYEN
ZA Case Cleared 2/9/2023 DANG NGUYEN
Address approval Cleared 2/22/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/23/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 2/27/2023 MATTHEW CRAIG
Sewer availability Cleared 4/10/2023 CARLOS AGUILERA
Low Impact Development Cleared 5/12/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 5/15/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Ebrahimi,, Amirhosin; Lic. No.: C92049 8619 RESEDA BLVD UNIT 304B      NORTHRIDGE, CA 91324

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Floor/Roof Diaphrgm/Shear Wall 6/9/2026   

Inspection Request History

Pre-Inspection 2/26/2026 Partial Inspection NICHOLAS TROWBRIDGE
Sewer 3/6/2026 Approved NICHOLAS TROWBRIDGE
Footing/Foundation/Slab 3/11/2026 Partial Approval NICHOLAS TROWBRIDGE
Sewer 3/11/2026 Partial Approval NICHOLAS TROWBRIDGE
Footing/Foundation/Slab 3/31/2026 Corrections Issued NICHOLAS TROWBRIDGE
Underground Mechanical 4/27/2026 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 5/8/2026 Partial Approval NICHOLAS TROWBRIDGE
PLUMBING-Rough 5/8/2026 Partial Approval NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 5/12/2026 Partial Approval NICHOLAS TROWBRIDGE