18345 W DOMINO ST 91335
Certificate Information: 18345 W DOMINO ST 91335
- Application / Permit
- 22010-20000-04312
- Plan Check / Job No.
- B22VN13131
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO A NEW (18'-3" x 19'-11") ACCESSROY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/24/2023
- Issuing Office
- Current Status
- CofO Issued on 1/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2022 | SARKIS HARABEDIAN |
| Corrections Issued | 9/10/2022 | SARKIS HARABEDIAN |
| Plan Check Approved | 1/9/2023 | SARKIS HARABEDIAN |
| Issued | 1/24/2023 | APPLICANT |
| CofO in Progress | 1/2/2024 | JON MCHUGH |
| Permit Finaled | 1/29/2024 | JOHN JANSON |
| CofO Issued | 1/29/2024 | JOHN JANSON |
| Permit Finaled | 1/29/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/26/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 9/26/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 9/27/2022 | COLIN LOREDO |
| Construction near power lines | Cleared | 12/3/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/3/2022 | RIDWAN HARDY |
Contact Information
| Architect | Di, Zitti, Fernando; Lic. No.: NA24587 | , |
| Contractor | Spiffy Construction; Lic. No.: 901156-B | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 2/23/2023 | Not Ready for Inspection | SEAN HAUPT |
| Sewer | 2/23/2023 | Approved | SEAN HAUPT |
| Deputy Drilled-In Anchors | 3/28/2023 | Approved | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 3/28/2023 | Approved | JON MCHUGH |
| Underground Mechanical | 6/8/2023 | Partial Approval | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 8/16/2023 | Corrections Issued | JON MCHUGH |
| Wood Frame | 8/16/2023 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 8/30/2023 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 8/30/2023 | Approved | JON MCHUGH |
| Insulation | 8/30/2023 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 8/30/2023 | Approved | JON MCHUGH |
| Wood Frame | 8/30/2023 | Partial Approval | JON MCHUGH |
| Insulation | 9/19/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 9/19/2023 | Approved | JOHN KIDWELL |
| Shower Pan | 9/19/2023 | Approved | JOHN KIDWELL |
| Pre-Inspection | 10/4/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 10/16/2023 | Approved | JON MCHUGH |
| Drywall Nailing | 10/30/2023 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 12/18/2023 | Approved | JON MCHUGH |
| Final | 12/18/2023 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 12/18/2023 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 12/18/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 12/27/2023 | Approved | JON MCHUGH |
| Final | 12/27/2023 | Partial Approval | JON MCHUGH |
| Green Building Final | 12/27/2023 | Approved | JON MCHUGH |
| HVAC-Final | 12/27/2023 | Approved | JON MCHUGH |
| PLUMBING-Final | 12/27/2023 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 12/27/2023 | SGSOV Approved | JON MCHUGH |
| Final | 1/2/2024 | OK to Issue CofO | JON MCHUGH |