14900 W EL CASCO ST 91342

Certificate Information: 14900 W EL CASCO ST 91342

Application / Permit
22010-20000-04311
Plan Check / Job No.
B22VN13130
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan PROPOSED 1 STORY ADU PER WFPP
Permit Issued
Issued on 2/9/2023
Issuing Office
Current Status
Issued on 2/9/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/29/2022 APPLICANT
Assigned to Plan Check Engineer 9/15/2022 CRYSTEL MAALOUF
Corrections Issued 9/22/2022 CRYSTEL MAALOUF
Quality Review Completed 9/27/2022 GARO TELMI
Applicant returned to address corrections 12/19/2022 CRYSTEL MAALOUF
Plan Check Approved 2/6/2023 CRYSTEL MAALOUF
Issued 2/9/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/12/2022 RYAN KIM
Watercourse Cleared 10/13/2022 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 10/25/2022 RYAN KIM
Sewer availability Cleared 11/3/2022 RYAN KIM
Zoning Information File Cleared 1/5/2023 DANIEL SCHNEIDEREIT
Roof/Waste drainage to street Cleared 1/24/2023 RYAN KIM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/17/2023 Partial Inspection ARAM AVEDISIAN
PLUMBING-Rough 6/9/2023 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 6/14/2023 Corrections Issued THOMAS FINNILA
Pre-Inspection 6/20/2023 Corrections Issued DAVID ANDERSON
Deputy Reinf. Concrete 6/21/2023 Conditional Approval ROBERT GOLD
Deputy Reinf. Concrete 6/22/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 6/26/2023 Corrections Issued ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 6/28/2023 Approved ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 8/28/2023 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 9/19/2023 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 9/19/2023 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 10/2/2023 Not Ready for Inspection KEVIN BERBERYAN
Sewer 10/2/2023 Approved KEVIN BERBERYAN
Shower Pan 10/2/2023 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 11/7/2023 Approved KEVIN BERBERYAN
Shower Pan 11/7/2023 Partial Inspection KEVIN BERBERYAN
ELECTRICAL-Rough 12/1/2023 Corrections Issued KEVIN BERBERYAN
HVAC-Rough 12/1/2023 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 12/18/2023 Approved MATTHEW NELSON
ELECTRICAL-Rough 12/18/2023 Approved MATTHEW NELSON
HVAC-Rough 12/18/2023 Approved MATTHEW NELSON
Insulation 1/11/2024 Conditional Approval KEVIN BERBERYAN
Drywall Nailing 1/23/2024 Approved ROBERT GOLD
Insulation 1/23/2024 Approved ROBERT GOLD
Gas Test 2/21/2024 Partial Approval CRAIG DAVIS
Final 7/25/2024 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 7/25/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 7/25/2024 SGSOV Approved KEVIN BERBERYAN
Service/Power Release 7/25/2024 Corrections Issued KEVIN BERBERYAN
Smoke Detectors 7/25/2024 Approved KEVIN BERBERYAN
Final 11/7/2024 Corrections Issued KEVIN BERBERYAN
Service/Power Release 11/7/2024 Not Ready for Inspection KEVIN BERBERYAN
Final 6/9/2025 Corrections Issued NICHOLAS TROWBRIDGE
Service/Power Release 6/9/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 7/8/2025 Corrections Issued KEVIN BERBERYAN
Service/Power Release 7/8/2025 Conditional Approval KEVIN BERBERYAN
Final 8/20/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 8/27/2025 Not Ready for Inspection KEVIN BERBERYAN
Service/Power Release 8/27/2025 Not Ready for Inspection KEVIN BERBERYAN