134-134 1/2 W 74TH ST 90003

Certificate Information: 134-134 1/2 W 74TH ST 90003

Application / Permit
22010-20000-04284
Plan Check / Job No.
B22VN13096
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan- NEW 2-STORY, 2-UNIT ADUs PER CA GOVT CODE 65852.2(e)(1)(D) & APPLICABLE PART OF LAMC 12.22 A.33 (c)-(d) &(g)
Permit Issued
Issued on 12/18/2024
Issuing Office
Current Status
CofO Issued on 3/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2022 APPLICANT
Assigned to Plan Check Engineer 9/15/2022 MAHNAZ NOURHASHEMI
Corrections Issued 9/22/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 9/30/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 9/27/2024 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 11/3/2024 MAHNAZ NOURHASHEMI
Plan Check Approved 11/21/2024 MAHNAZ NOURHASHEMI
Issued 12/18/2024 APPLICANT
CofO in Progress 3/3/2026 MICHAEL LEWIS
Permit Finaled 3/3/2026 DEROLD HAUFF
CofO Issued 3/3/2026 DEROLD HAUFF
Permit Finaled 3/3/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/29/2022 AMAAN MALIK
Sewer availability Cleared 11/29/2022 AMAAN MALIK
Address approval Cleared 1/19/2023 CELINA MORENO
Hydrant and Access approval Cleared 2/2/2023 MATTHEW CRAIG
Low Impact Development Cleared 9/17/2024 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 9/19/2024 CELINA MORENO

Contact Information

Contractor Mdr Builders; Lic. No.: 741228-B       ,
Engineer Zohrevand,, Pedram; Lic. No.: C82328 19562 VENTURA BLVD UNIT 238      TARZANA, CA 91356

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Interior/Exterior Lathing 12/30/2024 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Rough 12/30/2024 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 1/6/2025 Partial Approval NICHOLAS LOPEZ
Excavation/Setback/Form/Re-Bar 1/13/2025 Approved JOHN QUINTANILLA
Footing/Foundation/Slab 1/13/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 4/2/2025 Corrections Issued JOHN QUINTANILLA
HVAC-Rough 4/2/2025 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 4/2/2025 Approved JOHN QUINTANILLA
Wood Frame 4/2/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 4/10/2025 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Rough 4/10/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 4/10/2025 Not Ready for Inspection JOHN QUINTANILLA
Wood Frame 4/10/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 4/21/2025 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 4/21/2025 Approved MICHAEL LEWIS
Wood Frame 4/24/2025 Corrections Issued JOHN QUINTANILLA
Wood Frame 4/28/2025 Partial Approval JOHN QUINTANILLA
Insulation 5/2/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 5/5/2025 Approved JOHN QUINTANILLA
Drywall Nailing 5/8/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 5/15/2025 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 10/23/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 10/23/2025 Corrections Issued JOHN QUINTANILLA
PLUMBING-Final 10/23/2025 Approved JOHN QUINTANILLA
Verify Sprinkler Sign Off 10/23/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 10/30/2025 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Final 10/30/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Final 11/6/2025 Approved JOHN QUINTANILLA
HVAC-Final 11/6/2025 Approved JOHN QUINTANILLA
Final 1/23/2026 Corrections Issued JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 1/23/2026 SGSOV Not Ready JOHN QUINTANILLA
Service/Power Release 1/23/2026 Approved JOHN QUINTANILLA
Smoke Detectors 1/23/2026 Approved JOHN QUINTANILLA
Final 1/28/2026 Conditional Approval JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 1/28/2026 SGSOV Approved JOHN QUINTANILLA
Final 3/2/2026 OK to Issue CofO MICHAEL LEWIS