7632 N RIVERTON AVE 91352
Certificate Information: 7632 N RIVERTON AVE 91352
- Application / Permit
- 22010-20000-04274
- Plan Check / Job No.
- B22VN13047
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **EPLAN** NEW 1-Story Accessory Dwelling Unit (4 Bedroom, 2 Bathroom) per City Ordinance
- Permit Issued
- Issued on 3/17/2023
- Issuing Office
- Current Status
- CofO Issued on 2/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2022 | SHANGQIN XIE |
| Corrections Issued | 9/14/2022 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 10/11/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 3/8/2023 | JESSE JIMENEZ |
| Issued | 3/17/2023 | APPLICANT |
| CofO in Progress | 2/1/2024 | MATTHEW NELSON |
| Permit Finaled | 2/23/2024 | RUBEN SALAS |
| CofO Issued | 2/23/2024 | RUBEN SALAS |
| Permit Finaled | 2/23/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/5/2022 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 1/31/2023 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 2/9/2023 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 2/14/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 3/3/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/25/2023 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 4/28/2023 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 5/16/2023 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 5/16/2023 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/29/2023 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 6/29/2023 | Approved | MATTHEW NELSON |
| Green Building Rough | 6/29/2023 | Approved | MATTHEW NELSON |
| HVAC-Rough | 6/29/2023 | Corrections Issued | MATTHEW NELSON |
| Interior/Exterior Lathing | 6/29/2023 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 6/29/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 6/29/2023 | Approved | MATTHEW NELSON |
| HVAC-Rough | 7/5/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 7/5/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/22/2023 | Approved | MATTHEW NELSON |
| Insulation | 8/22/2023 | Partial Approval | MATTHEW NELSON |
| Drywall Nailing | 8/29/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 8/29/2023 | Partial Approval | WILLIAM WREN |
| ELECTRICAL-Final | 9/26/2023 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Final | 9/26/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Underground Mechanical | 9/26/2023 | Approved | DAVID ANDERSON |
| Final | 11/21/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 11/21/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 11/21/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Smoke Detectors | 11/21/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 12/26/2023 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 12/26/2023 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/26/2023 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 12/26/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 12/26/2023 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Final | 1/4/2024 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Final | 1/12/2024 | Approved | KEVIN BERBERYAN |
| Final | 1/31/2024 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 1/31/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/31/2024 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 1/31/2024 | Approved | MATTHEW NELSON |
| Smoke Detectors | 1/31/2024 | Approved | MATTHEW NELSON |