1261-1263 E 25TH ST 90011

Certificate Information: 1261-1263 E 25TH ST 90011

Application / Permit
22010-20000-04271
Plan Check / Job No.
B22VN13033
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ePLAN. CONVERT (E) ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 12/1/2022
Issuing Office
Current Status
CofO Issued on 5/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2022 APPLICANT
Assigned to Plan Check Engineer 8/26/2022 KEVIN MORALES
Corrections Issued 8/26/2022 KEVIN MORALES
Plan Check Approved 10/4/2022 KEVIN MORALES
Issued 12/1/2022 APPLICANT
CofO in Progress 5/1/2024 ALFREDO LOPEZ
Permit Finaled 5/13/2024 ERNESTO CORRAL
CofO Issued 5/13/2024 ERNESTO CORRAL
Permit Finaled 5/13/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 9/17/2022 STEVE MELGAR
Sewer availability Cleared 9/17/2022 STEVE MELGAR
"Q" conditions Cleared 9/21/2022 JAZMIN ROQUE
Eng Process Fee Ord 176,300 Cleared 11/30/2022 AMY SHUM

Contact Information

Contractor C I D Builders And Developers Inc; Lic. No.: 958193-B       ,

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 12/7/2022 Not Ready for Inspection ALAN MORELOS
Wood Frame 12/7/2022 Corrections Issued ALAN MORELOS
Green Building Rough 12/12/2022 Not Ready for Inspection ALAN MORELOS
Wood Frame 12/12/2022 Not Ready for Inspection ALAN MORELOS
Footing/Foundation/Slab 12/28/2022 Approved ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 1/26/2023 Partial Approval ALAN MORELOS
Green Building Rough 1/26/2023 Not Ready for Inspection ALAN MORELOS
Green Building Rough 6/6/2023 No Access for Inspection ALAN MORELOS
Wood Frame 6/6/2023 No Access for Inspection ALAN MORELOS
Green Building Rough 6/8/2023 Approved ALAN MORELOS
Interior/Exterior Lathing 6/8/2023 Partial Approval ALAN MORELOS
Insulation 6/30/2023 Approved ALAN MORELOS
Drywall Nailing 8/1/2023 Approved ALAN MORELOS
Insulation 8/1/2023 Approved ALAN MORELOS
Interior/Exterior Lathing 8/14/2023 Approved MARTIN TAVITIAN
Final 10/19/2023 Not Ready for Inspection VAHE KELEDJIAN
Green Building Final 10/19/2023 Not Ready for Inspection VAHE KELEDJIAN
SGSOV-Seismic Gas S/O Valve 10/19/2023 SGSOV Not Ready VAHE KELEDJIAN
Smoke Detectors 10/19/2023 Not Ready for Inspection VAHE KELEDJIAN
Wood Frame 10/19/2023 Not Ready for Inspection VAHE KELEDJIAN
Final 2/9/2024 Not Ready for Inspection MARTIN TAVITIAN
Green Building Final 2/9/2024 Approved MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 2/9/2024 SGSOV Approved MARTIN TAVITIAN
Smoke Detectors 2/9/2024 Not Ready for Inspection MARTIN TAVITIAN
Wood Frame 2/9/2024 Not Ready for Inspection MARTIN TAVITIAN
Final 3/1/2024 Not Ready for Inspection LUIS CCAMACHO
Smoke Detectors 3/1/2024 Approved LUIS CCAMACHO
Wood Frame 3/1/2024 Not Ready for Inspection LUIS CCAMACHO
Final 3/14/2024 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 3/14/2024 Not Ready for Inspection ALFREDO LOPEZ
Final 4/26/2024 OK to Issue CofO ALFREDO LOPEZ
Wood Frame 4/26/2024 Approved ALFREDO LOPEZ