- ePLAN. CONVERT (E) ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 12/1/2022
- Issuing Office
- Current Status
- CofO Issued on 5/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2022 | KEVIN MORALES |
| Corrections Issued | 8/26/2022 | KEVIN MORALES |
| Plan Check Approved | 10/4/2022 | KEVIN MORALES |
| Issued | 12/1/2022 | APPLICANT |
| CofO in Progress | 5/1/2024 | ALFREDO LOPEZ |
| Permit Finaled | 5/13/2024 | ERNESTO CORRAL |
| CofO Issued | 5/13/2024 | ERNESTO CORRAL |
| Permit Finaled | 5/13/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 9/17/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 9/17/2022 | STEVE MELGAR |
| "Q" conditions | Cleared | 9/21/2022 | JAZMIN ROQUE |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2022 | AMY SHUM |
Contact Information
| Contractor | C I D Builders And Developers Inc; Lic. No.: 958193-B | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 12/7/2022 | Not Ready for Inspection | ALAN MORELOS |
| Wood Frame | 12/7/2022 | Corrections Issued | ALAN MORELOS |
| Green Building Rough | 12/12/2022 | Not Ready for Inspection | ALAN MORELOS |
| Wood Frame | 12/12/2022 | Not Ready for Inspection | ALAN MORELOS |
| Footing/Foundation/Slab | 12/28/2022 | Approved | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2023 | Partial Approval | ALAN MORELOS |
| Green Building Rough | 1/26/2023 | Not Ready for Inspection | ALAN MORELOS |
| Green Building Rough | 6/6/2023 | No Access for Inspection | ALAN MORELOS |
| Wood Frame | 6/6/2023 | No Access for Inspection | ALAN MORELOS |
| Green Building Rough | 6/8/2023 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 6/8/2023 | Partial Approval | ALAN MORELOS |
| Insulation | 6/30/2023 | Approved | ALAN MORELOS |
| Drywall Nailing | 8/1/2023 | Approved | ALAN MORELOS |
| Insulation | 8/1/2023 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 8/14/2023 | Approved | MARTIN TAVITIAN |
| Final | 10/19/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Green Building Final | 10/19/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 10/19/2023 | SGSOV Not Ready | VAHE KELEDJIAN |
| Smoke Detectors | 10/19/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Wood Frame | 10/19/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Final | 2/9/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Green Building Final | 2/9/2024 | Approved | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 2/9/2024 | SGSOV Approved | MARTIN TAVITIAN |
| Smoke Detectors | 2/9/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Wood Frame | 2/9/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Final | 3/1/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Smoke Detectors | 3/1/2024 | Approved | LUIS CCAMACHO |
| Wood Frame | 3/1/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Final | 3/14/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 3/14/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 4/26/2024 | OK to Issue CofO | ALFREDO LOPEZ |
| Wood Frame | 4/26/2024 | Approved | ALFREDO LOPEZ |