17177 W ADLON ROAD 91436
Certificate Information: 17177 W ADLON ROAD 91436
- Application / Permit
- 22010-20000-04251
- Plan Check / Job No.
- B22VN12951
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 82'6" X 79'6" 2-STORY SFD WITH FOUR CAR GARAGE, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 9/12/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | RARES BODEA |
| Corrections Issued | 9/6/2022 | RARES BODEA |
| Quality Review Completed | 9/8/2022 | STEVEN KIM |
| Building Plans Picked Up | 9/12/2022 | APPLICANT |
| Applicant returned to address corrections | 11/1/2022 | RARES BODEA |
| Plan Check Approved | 5/23/2023 | RARES BODEA |
| Issued | 9/12/2023 | APPLICANT |
| CofO in Progress | 1/22/2025 | THOMAS FINNILA |
| No Progress | 2/27/2025 | SEAN WIRCH |
| CofO in Progress | 2/27/2025 | SEAN WIRCH |
| CofO in Progress | 3/11/2025 | SEAN WIRCH |
| CofO Issued | 3/12/2025 | JOHN JANSON |
| Permit Finaled | 3/12/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/20/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 9/20/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 9/20/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 9/20/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 9/20/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 9/20/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/20/2022 | CARLOS AGUILERA |
| ZA Case | Cleared | 10/4/2022 | MIGUEL GAMBOA |
| GPI Written Notices | Cleared | 11/1/2022 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 11/1/2022 | RARES BODEA |
| Distance to fire station | Cleared | 11/23/2022 | MATTHEW CRAIG |
| Hydrant and Access approval | Cleared | 11/23/2022 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 5/7/2023 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 5/8/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/22/2024 | Approved | VINCENT HANLEY |
| Sewer | 1/22/2024 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 1/29/2024 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 1/29/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 1/29/2024 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 1/30/2024 | Partial Approval | VINCENT HANLEY |
| Deputy Wood Construction | 4/16/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2024 | Partial Approval | VINCENT HANLEY |
| Deputy Wood Construction | 5/7/2024 | Partial Approval | VINCENT HANLEY |
| Deputy Wood Construction | 5/28/2024 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2024 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2024 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 6/7/2024 | Corrections Issued | THOMAS FINNILA |
| Gas Test | 6/18/2024 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 6/18/2024 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 6/24/2024 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2024 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/27/2024 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 6/27/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 6/27/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 7/2/2024 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/5/2024 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 7/5/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 7/5/2024 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 7/9/2024 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/17/2024 | Approved | THOMAS FINNILA |
| Green Building Rough | 7/17/2024 | Approved | THOMAS FINNILA |
| Insulation | 7/23/2024 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 8/2/2024 | Approved | THOMAS FINNILA |
| Gas Test | 8/2/2024 | Conditional Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/2/2024 | Approved | THOMAS FINNILA |
| Gas Test | 11/6/2024 | Approved | MORRIS JACKSON |
| HVAC-Final | 12/17/2024 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Final | 12/24/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Final | 12/24/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Service/Power Release | 12/24/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| ELECTRICAL-Final | 12/26/2024 | Partial Approval | THOMAS FINNILA |
| HVAC-Final | 12/26/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 12/26/2024 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 1/7/2025 | Approved | THOMAS FINNILA |
| Final | 1/7/2025 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 1/7/2025 | Approved | THOMAS FINNILA |
| HVAC-Final | 1/7/2025 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 1/7/2025 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 1/7/2025 | SGSOV Approved | THOMAS FINNILA |
| Service/Power Release | 1/7/2025 | Approved | THOMAS FINNILA |
| Smoke Detectors | 1/7/2025 | Approved | THOMAS FINNILA |
| Final | 1/21/2025 | OK to Issue CofO | THOMAS FINNILA |