7313 N SHOUP AVE 91307
Certificate Information: 7313 N SHOUP AVE 91307
- Application / Permit
- 22010-20000-04249
- Plan Check / Job No.
- B22VN12949
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN GARAGE ADDITION AND CONVERSION TO NEW ADU PER LAMC 12.22 A.33(c)(d) ALL WORK DONE PER WFPP
- Permit Issued
- Issued on 9/9/2022
- Issuing Office
- Current Status
- CofO Corrected on 3/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2022 | KHUONG TRUONG |
| Corrections Issued | 8/31/2022 | KHUONG TRUONG |
| Plan Check Approved | 9/2/2022 | KHUONG TRUONG |
| Issued | 9/9/2022 | APPLICANT |
| CofO in Progress | 2/22/2023 | CHRIS CHRISTENSEN |
| Re-Activate Permit | 3/15/2023 | JOHN JANSON |
| CofO Issued-Status Void | 3/15/2023 | JOHN JANSON |
| Permit Finaled-Status Void | 3/15/2023 | JOHN JANSON |
| Permit Finaled | 3/15/2023 | JOHN JANSON |
| CofO Corrected | 3/15/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/1/2022 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2022 | FERNANDO GIL |
| Roof/Waste drainage to street | Cleared | 9/1/2022 | FERNANDO GIL |
| Sewer availability | Cleared | 9/1/2022 | FERNANDO GIL |
Contact Information
| Contractor | Markarian Setrag; Lic. No.: 832632-B | , |
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/20/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 9/21/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 9/21/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Wood Frame | 10/13/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 11/4/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 11/4/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 11/9/2022 | Partial Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 11/9/2022 | Approved | CHRIS CHRISTENSEN |
| Insulation | 11/9/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 11/9/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 11/17/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 11/17/2022 | Approved | CHRIS CHRISTENSEN |
| Insulation | 11/17/2022 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 11/17/2022 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 11/17/2022 | Partial Inspection | MORRIS JACKSON |
| Drywall Nailing | 11/30/2022 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 12/30/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 2/3/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 2/3/2023 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 2/3/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 2/3/2023 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 2/3/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 2/9/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 2/9/2023 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 2/9/2023 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Final | 2/21/2023 | OK to Issue CofO | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 2/21/2023 | SGSOV Approved | CHRIS CHRISTENSEN |