6328 N CLEON AVE 91606

Certificate Information: 6328 N CLEON AVE 91606

Application / Permit
22010-20000-04244
Plan Check / Job No.
B22VN12944
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* NEW 27' X 47' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 1/23/2023
Issuing Office
Current Status
CofO Issued on 11/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2022 APPLICANT
Assigned to Plan Check Engineer 9/9/2022 SELLA BENYAMIN
Corrections Issued 9/11/2022 SELLA BENYAMIN
Quality Review Completed 9/21/2022 STEVEN KIM
Plan Check Approved 1/19/2023 SELLA BENYAMIN
Issued 1/23/2023 APPLICANT
CofO in Progress 10/5/2023 JOHN HAYES
Permit Finaled 11/27/2023 RUBEN SALAS
CofO Issued 11/27/2023 RUBEN SALAS
Permit Finaled 11/27/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/26/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/9/2022 CARLOS AGUILERA
Low Impact Development Cleared 11/9/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 11/9/2022 CARLOS AGUILERA
Sewer availability Cleared 11/9/2022 CARLOS AGUILERA
Construction near power lines Cleared 1/9/2023 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/2/2023 Approved JOHN HAYES
Excavation/Setback/Form/Re-Bar 3/13/2023 Approved MISAEL ESPARZA
Footing/Foundation/Slab 3/13/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 4/6/2023 Not Ready for Inspection MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 4/6/2023 Partial Approval MATTHEW NELSON
Green Building Rough 4/6/2023 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 4/6/2023 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 5/11/2023 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 5/11/2023 Partial Approval JOHN HAYES
HVAC-Rough 5/11/2023 Approved JOHN HAYES
PLUMBING-Rough 5/11/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 5/19/2023 Approved JOHN HAYES
Green Building Rough 5/19/2023 Approved JOHN HAYES
Interior/Exterior Lathing 5/19/2023 Partial Approval JOHN HAYES
Shower Pan 5/19/2023 Approved JOHN HAYES
Verify Sprinkler Sign Off 5/19/2023 Approved JOHN HAYES
Insulation 5/26/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/26/2023 Approved RYAN SALAZAR
Drywall Nailing 6/6/2023 Approved JOHN HAYES
Final 8/25/2023 Corrections Issued JOHN HAYES
Final 10/2/2023 Corrections Issued JOHN HAYES
Green Building Final 10/2/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 10/2/2023 SGSOV Not Ready JOHN HAYES
Service/Power Release 10/2/2023 Not Ready for Inspection JOHN HAYES
Smoke Detectors 10/2/2023 Approved JOHN HAYES
Final 10/5/2023 OK to Issue CofO JOHN HAYES
Gas Test 10/5/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 10/5/2023 SGSOV Approved JOHN HAYES
Service/Power Release 10/5/2023 Approved JOHN HAYES