5105 N OAKDALE AVE 91364

Certificate Information: 5105 N OAKDALE AVE 91364

Application / Permit
22010-20000-04235
Plan Check / Job No.
B22VN12919
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 16'-3 9/16" x 17'-9 1/16" DET. REC ROOM
Permit Issued
Issued on 10/25/2022
Issuing Office
Current Status
CofO in Progress on 1/31/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/24/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 SEAN SHAHMIRI
Corrections Issued 9/5/2022 SEAN SHAHMIRI
Quality Review Completed 9/9/2022 OMID HEDAYAT
Building Plans Picked Up 9/13/2022 APPLICANT
Applicant returned to address corrections 10/13/2022 SEAN SHAHMIRI
Applicant returned to address corrections 10/20/2022 SEAN SHAHMIRI
Plan Check Approved 10/25/2022 SEAN SHAHMIRI
Issued 10/25/2022 APPLICANT
CofO in Progress 4/5/2024 MORRIS JACKSON
CofO in Progress 5/2/2024 SEAN WIRCH
No Progress 1/31/2025 SEAN WIRCH
CofO in Progress 1/31/2025 SEAN WIRCH

Permit Application Clearance Information

Sewer availability Cleared 9/8/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/13/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 10/4/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 10/4/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/27/2023 Approved PETER FOLLING
PLUMBING-Rough 7/27/2023 Partial Approval PETER FOLLING
Sewer 7/27/2023 Approved PETER FOLLING
ELECTRICAL-Rough 9/5/2023 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 9/5/2023 Corrections Issued SEAN HAUPT
HVAC-Rough 9/5/2023 Not Ready for Inspection SEAN HAUPT
Interior/Exterior Lathing 9/5/2023 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 9/5/2023 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 9/27/2023 Not Ready for Inspection PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 9/27/2023 Corrections Issued PETER FOLLING
HVAC-Rough 9/27/2023 Corrections Issued PETER FOLLING
Interior/Exterior Lathing 9/27/2023 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 9/27/2023 Approved PETER FOLLING
ELECTRICAL-Rough 9/28/2023 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 9/28/2023 Approved PETER FOLLING
Gas Test 9/28/2023 Approved PETER FOLLING
Shower Pan 9/28/2023 Approved PETER FOLLING
Drywall Nailing 10/25/2023 Corrections Issued PETER FOLLING
BUILDING-Rough-Frame 11/1/2023 Approved PETER FOLLING
Drywall Nailing 11/1/2023 Approved PETER FOLLING
Green Building Rough 11/1/2023 Approved PETER FOLLING
HVAC-Rough 11/1/2023 Approved PETER FOLLING
Insulation 11/1/2023 Approved PETER FOLLING
Verify Sprinkler Sign Off 11/1/2023 Approved PETER FOLLING
Gas Test 2/29/2024 Approved MORRIS JACKSON
HVAC-Final 2/29/2024 Approved MORRIS JACKSON
PLUMBING-Final 2/29/2024 Approved MORRIS JACKSON
ELECTRICAL-Final 3/12/2024 Approved MORRIS JACKSON
Final 3/12/2024 Corrections Issued MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 3/12/2024 SGSOV Not Ready MORRIS JACKSON
Service/Power Release 3/12/2024 Not Ready for Inspection MORRIS JACKSON
Smoke Detectors 3/12/2024 Approved MORRIS JACKSON
Final 4/4/2024 OK to Issue CofO MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 4/4/2024 SGSOV Approved MORRIS JACKSON
Service/Power Release 4/4/2024 Approved MORRIS JACKSON