7818 N LASAINE AVE 91325
Certificate Information: 7818 N LASAINE AVE 91325
- Application / Permit
- 22010-20000-04232
- Plan Check / Job No.
- B22VN12909
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY (42'-0"x30'-3"), 1200 SQFT ACCESSORY DWELLING UNIT PER LAMC
- Permit Issued
- Issued on 4/14/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2022 | PETER MOSESIAN |
| Corrections Issued | 9/14/2022 | PETER MOSESIAN |
| Quality Review Completed | 9/21/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 9/23/2022 | APPLICANT |
| Plan Check Approved | 2/21/2023 | PETER MOSESIAN |
| Issued | 4/14/2023 | APPLICANT |
| CofO in Progress | 10/31/2023 | RAUL OLAGI |
| CofO Issued | 11/28/2023 | RUBEN SALAS |
| Permit Finaled | 11/28/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/26/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/27/2022 | ROMAN GUTIERREZ |
| Senate Bill 9 | Cleared | 9/28/2022 | NELSON RODRIGUEZ |
| Sewer availability | Cleared | 9/28/2022 | ROMAN GUTIERREZ |
| Construction near power lines | Cleared | 10/13/2022 | WALTER RAMIREZ |
| Hydrant and Access approval | Cleared | 10/28/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 12/13/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 12/15/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/23/2023 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 5/23/2023 | Partial Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 5/25/2023 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 5/25/2023 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2023 | Corrections Issued | RAUL OLAGI |
| Sewer | 6/2/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 6/2/2023 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2023 | Partial Approval | ROBERT GOLD |
| PLUMBING-Rough | 6/6/2023 | Not Ready for Inspection | ROBERT GOLD |
| BUILDING-Rough-Frame | 6/28/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 6/28/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 6/28/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 6/28/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 6/28/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 6/28/2023 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 6/28/2023 | Approved | RAUL OLAGI |
| Insulation | 7/11/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 7/11/2023 | Partial Approval | RAUL OLAGI |
| Shower Pan | 7/11/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 7/20/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/20/2023 | Approved | DAVID ANDERSON |
| Pre-Inspection | 8/9/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 10/23/2023 | Corrections Issued | RAUL OLAGI |
| Final | 10/23/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 10/23/2023 | Approved | RAUL OLAGI |
| HVAC-Final | 10/23/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 10/23/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 10/23/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 10/23/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 10/30/2023 | Approved | RAUL OLAGI |
| Final | 10/30/2023 | OK to Issue CofO | RAUL OLAGI |
| HVAC-Final | 10/30/2023 | Approved | RAUL OLAGI |
| Service/Power Release | 10/30/2023 | Approved | RAUL OLAGI |