7818 N LASAINE AVE 91325

Certificate Information: 7818 N LASAINE AVE 91325

Application / Permit
22010-20000-04232
Plan Check / Job No.
B22VN12909
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY (42'-0"x30'-3"), 1200 SQFT ACCESSORY DWELLING UNIT PER LAMC
Permit Issued
Issued on 4/14/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2022 APPLICANT
Assigned to Plan Check Engineer 9/8/2022 PETER MOSESIAN
Corrections Issued 9/14/2022 PETER MOSESIAN
Quality Review Completed 9/21/2022 OMID HEDAYAT
Building Plans Picked Up 9/23/2022 APPLICANT
Plan Check Approved 2/21/2023 PETER MOSESIAN
Issued 4/14/2023 APPLICANT
CofO in Progress 10/31/2023 RAUL OLAGI
CofO Issued 11/28/2023 RUBEN SALAS
Permit Finaled 11/28/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/26/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 9/27/2022 ROMAN GUTIERREZ
Senate Bill 9 Cleared 9/28/2022 NELSON RODRIGUEZ
Sewer availability Cleared 9/28/2022 ROMAN GUTIERREZ
Construction near power lines Cleared 10/13/2022 WALTER RAMIREZ
Hydrant and Access approval Cleared 10/28/2022 GILBERT URREA
Low Impact Development Cleared 12/13/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 12/15/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/23/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 5/23/2023 Partial Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 5/25/2023 Approved RAUL OLAGI
Footing/Foundation/Slab 5/25/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 6/2/2023 Corrections Issued RAUL OLAGI
Sewer 6/2/2023 Approved RAUL OLAGI
Underground Mechanical 6/2/2023 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 6/6/2023 Partial Approval ROBERT GOLD
PLUMBING-Rough 6/6/2023 Not Ready for Inspection ROBERT GOLD
BUILDING-Rough-Frame 6/28/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 6/28/2023 Approved RAUL OLAGI
Green Building Rough 6/28/2023 Approved RAUL OLAGI
HVAC-Rough 6/28/2023 Approved RAUL OLAGI
PLUMBING-Rough 6/28/2023 Approved RAUL OLAGI
Underground Mechanical 6/28/2023 Approved RAUL OLAGI
Verify Sprinkler Sign Off 6/28/2023 Approved RAUL OLAGI
Insulation 7/11/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 7/11/2023 Partial Approval RAUL OLAGI
Shower Pan 7/11/2023 Approved RAUL OLAGI
Drywall Nailing 7/20/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 7/20/2023 Approved DAVID ANDERSON
Pre-Inspection 8/9/2023 Approved RAUL OLAGI
ELECTRICAL-Final 10/23/2023 Corrections Issued RAUL OLAGI
Final 10/23/2023 Corrections Issued RAUL OLAGI
Green Building Final 10/23/2023 Approved RAUL OLAGI
HVAC-Final 10/23/2023 Corrections Issued RAUL OLAGI
PLUMBING-Final 10/23/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 10/23/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 10/23/2023 Approved RAUL OLAGI
ELECTRICAL-Final 10/30/2023 Approved RAUL OLAGI
Final 10/30/2023 OK to Issue CofO RAUL OLAGI
HVAC-Final 10/30/2023 Approved RAUL OLAGI
Service/Power Release 10/30/2023 Approved RAUL OLAGI