9046 N TERHUNE AVE 91352

Certificate Information: 9046 N TERHUNE AVE 91352

Application / Permit
22010-20000-04226
Plan Check / Job No.
B22VN12896
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (25'-0"x34'-0"), 792 SQFT SINGLE FAMILY DWELLING W/NFPA 13D SPRINKLERS THROUGHOUT PER SB9
Permit Issued
Issued on 8/1/2023
Issuing Office
Current Status
CofO Issued on 10/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 PETER MOSESIAN
Corrections Issued 8/27/2022 PETER MOSESIAN
Quality Review Completed 8/31/2022 OMID HEDAYAT
Building Plans Picked Up 9/2/2022 APPLICANT
Plan Check Approved 8/1/2023 PETER MOSESIAN
Issued 8/1/2023 APPLICANT
CofO in Progress 10/1/2024 DAVID ANDERSON
Permit Finaled 10/22/2024 DANIEL ORRANTE
CofO Issued 10/22/2024 DANIEL ORRANTE
Permit Finaled 10/22/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/11/2022 LEE GUILBEAUX
Sewer availability Cleared 10/12/2022 LEE GUILBEAUX
Senate Bill 9 Cleared 12/14/2022 DANG NGUYEN
Low Impact Development Cleared 1/20/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 2/8/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/22/2023 LEE GUILBEAUX
Hydrant and Access approval Cleared 2/24/2023 GILBERT URREA
Specific Plan Cleared 2/27/2023 CECILIA CASTILLO
ZI Cleared 2/27/2023 CECILIA CASTILLO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/30/2023 Corrections Issued DAVID ANDERSON
Underground Mechanical 11/30/2023 Not Ready for Inspection DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 12/7/2023 Not Ready for Inspection MATTHEW NELSON
Underground Mechanical 12/7/2023 Partial Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 12/13/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 1/12/2024 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 1/12/2024 Approved DAVID ANDERSON
Green Building Rough 1/12/2024 Not Ready for Inspection DAVID ANDERSON
Verify Sprinkler Sign Off 1/12/2024 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 1/30/2024 Approved DAVID ANDERSON
Sewer 1/30/2024 Approved DAVID ANDERSON
Underground Mechanical 1/30/2024 Partial Approval DAVID ANDERSON
ELECTRICAL-Rough 2/9/2024 Corrections Issued CRAIG DAVIS
Underground Mechanical 2/9/2024 Approved CRAIG DAVIS
ELECTRICAL-Rough 2/20/2024 Approved DAVID ANDERSON
HVAC-Rough 2/20/2024 Approved DAVID ANDERSON
BUILDING-Rough-Frame 3/4/2024 Approved DAVID ANDERSON
Green Building Rough 3/4/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 3/4/2024 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 3/4/2024 Approved DAVID ANDERSON
Shower Pan 3/12/2024 Approved DAVID ANDERSON
Insulation 4/4/2024 Approved DAVID ANDERSON
Drywall Nailing 4/10/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 4/29/2024 Approved DAVID ANDERSON
Underground Mechanical 5/22/2024 Approved DAVID ANDERSON
Underground Mechanical 5/23/2024 Approved DAVID ANDERSON
Final 7/8/2024 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 7/8/2024 Approved DAVID ANDERSON
Green Building Final 7/8/2024 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 7/8/2024 SGSOV Approved DAVID ANDERSON
Service/Power Release 7/8/2024 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 7/8/2024 Approved DAVID ANDERSON
Final 9/19/2024 Corrections Issued DAVID ANDERSON
Green Building Final 9/19/2024 Not Ready for Inspection DAVID ANDERSON
Service/Power Release 9/19/2024 Not Ready for Inspection DAVID ANDERSON
Structural Steel Frame 9/19/2024 Approved DAVID ANDERSON
Final 9/30/2024 OK to Issue CofO DAVID ANDERSON
Green Building Final 9/30/2024 Approved DAVID ANDERSON
Service/Power Release 9/30/2024 Approved DAVID ANDERSON