7327 N WHITAKER AVE 91406

Certificate Information: 7327 N WHITAKER AVE 91406

Application / Permit
22010-20000-04198
Plan Check / Job No.
B22VN12811
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story single family home with attached garage
Permit Issued
Issued on 9/13/2023
Issuing Office
Current Status
CofO Issued on 5/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2022 APPLICANT
Assigned to Plan Check Engineer 9/6/2022 HERNAN ARREOLA
Corrections Issued 9/16/2022 HERNAN ARREOLA
Quality Review Completed 9/23/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 10/14/2022 HERNAN ARREOLA
Plan Check Approved 1/9/2023 HERNAN ARREOLA
Plan Check Approved 9/12/2023 INTERNET PERMIT
Issued 9/13/2023 APPLICANT
CofO in Progress 4/3/2025 SALVADOR MARTINEZ
Permit Finaled 5/6/2025 RUBEN SALAS
CofO Issued 5/6/2025 RUBEN SALAS
Permit Finaled 5/6/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/28/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/28/2022 CARLOS AGUILERA
Sewer availability Cleared 9/28/2022 CARLOS AGUILERA
Tract Map conditions Cleared 9/30/2022 NATHAN ROMINE
Low Impact Development Cleared 10/31/2022 ERNEST TSE
Roof/Waste drainage to street Cleared 10/31/2022 CARLOS AGUILERA
Permit Cleared 11/2/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 11/13/2022 JOHN CONNEALLY

Contact Information

Architect Myer,, Jamie Beekman; Lic. No.: C31042 1730 3/4 WESTWOOD BLVD      LOS ANGELES, CA 90024
Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/25/2023 Approved RAUL OLAGI
Excavation/Setback/Form/Re-Bar 10/19/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 10/24/2023 Partial Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 11/1/2023 Not Ready for Inspection RAUL OLAGI
Footing/Foundation/Slab 11/3/2023 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 11/7/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/20/2023 Partial Approval MICHEL ABAJAN
Deputy Wood Construction 3/13/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/14/2024 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/22/2024 Partial Approval RAUL OLAGI
Deputy Steel/Welding 4/8/2024 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 4/19/2024 Approved RAUL OLAGI
ELECTRICAL-Rough 4/19/2024 Approved RAUL OLAGI
HVAC-Rough 4/19/2024 Approved RAUL OLAGI
PLUMBING-Rough 4/19/2024 Approved RAUL OLAGI
Verify Sprinkler Sign Off 4/19/2024 Approved RAUL OLAGI
Green Building Rough 5/10/2024 Approved RAUL OLAGI
Insulation 5/10/2024 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 5/10/2024 Corrections Issued RAUL OLAGI
Shower Pan 5/10/2024 Approved RAUL OLAGI
Drywall Nailing 5/21/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 5/21/2024 Approved MATTHEW NELSON
Sewer 8/2/2024 Approved SALVADOR MARTINEZ
Underground Mechanical 8/6/2024 Approved SALVADOR MARTINEZ
Service/Power Release 9/26/2024 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Final 10/1/2024 Corrections Issued SALVADOR MARTINEZ
Gas Test 10/1/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Final 10/1/2024 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Final 11/1/2024 Approved GAREN HAYRAPETYAN
Gas Test 11/1/2024 Approved GAREN HAYRAPETYAN
HVAC-Final 11/1/2024 Approved GAREN HAYRAPETYAN
PLUMBING-Final 11/1/2024 Approved GAREN HAYRAPETYAN
Service/Power Release 11/13/2024 Approved GAREN HAYRAPETYAN
Final 3/27/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 3/27/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 3/27/2025 SGSOV Not Ready GAREN HAYRAPETYAN
Smoke Detectors 3/27/2025 Approved GAREN HAYRAPETYAN
Final 4/2/2025 OK to Issue CofO SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 4/2/2025 SGSOV Approved SALVADOR MARTINEZ