8227 N WILKINSON AVE 91605

Certificate Information: 8227 N WILKINSON AVE 91605

Application / Permit
22010-20000-04190
Plan Check / Job No.
B22VN12785
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 22'-4" X 40' TWO STORY IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy."
Permit Issued
Issued on 9/20/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 SELLA BENYAMIN
Corrections Issued 8/30/2022 SELLA BENYAMIN
Quality Review Completed 9/1/2022 STEVEN KIM
Building Plans Picked Up 9/2/2022 APPLICANT
Plan Check Approved 9/20/2022 SELLA BENYAMIN
Issued 9/20/2022 APPLICANT
CofO in Progress 3/22/2024 MATTHEW NELSON
Permit Finaled 4/3/2024 RUBEN SALAS
CofO Issued 4/3/2024 RUBEN SALAS
Permit Finaled 4/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/6/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 9/7/2022 MEGAN GODINEZ
Sewer availability Cleared 9/7/2022 MEGAN GODINEZ
Construction near power lines Cleared 9/20/2022 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 9/20/2022 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/3/2022 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 11/15/2022 Approved CHRISTOPHER DELLEFIELD
Pre-Inspection 11/15/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 12/15/2022 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 1/11/2023 Corrections Issued MATTHEW NELSON
Pre-Inspection 1/27/2023 Approved MATTHEW NELSON
Rough-Elec/Plmb/HVAC 2/21/2023 Partial Approval MATTHEW NELSON
Wood Frame 2/21/2023 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 3/2/2023 Partial Approval MATTHEW NELSON
Green Building Rough 3/2/2023 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 3/2/2023 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 3/2/2023 Approved MATTHEW NELSON
BUILDING-Rough-Frame 5/3/2023 Approved MATTHEW NELSON
Green Building Rough 5/3/2023 Approved MATTHEW NELSON
ELECTRICAL-Rough 5/11/2023 Partial Approval MATTHEW NELSON
PLUMBING-Rough 5/11/2023 Partial Approval MATTHEW NELSON
Sewer 5/11/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 6/6/2023 Approved DAVID ANDERSON
Shower Pan 6/6/2023 Approved DAVID ANDERSON
Insulation 6/27/2023 Approved WILLIAM WREN
Drywall Nailing 7/5/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/5/2023 Approved MATTHEW NELSON
ELECTRICAL-Final 12/7/2023 Approved MATTHEW NELSON
HVAC-Final 12/7/2023 Approved MATTHEW NELSON
Final 1/26/2024 Not Ready for Inspection MATTHEW NELSON
Green Building Final 1/26/2024 Approved MATTHEW NELSON
PLUMBING-Final 1/26/2024 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 1/26/2024 SGSOV Approved MATTHEW NELSON
Service/Power Release 1/26/2024 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 1/26/2024 Approved MATTHEW NELSON
ELECTRICAL-Final 3/22/2024 Approved MATTHEW NELSON
Final 3/22/2024 OK to Issue CofO MATTHEW NELSON
Service/Power Release 3/22/2024 Approved MATTHEW NELSON