8227 N WILKINSON AVE 91605
Certificate Information: 8227 N WILKINSON AVE 91605
- Application / Permit
- 22010-20000-04190
- Plan Check / Job No.
- B22VN12785
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 22'-4" X 40' TWO STORY IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy."
- Permit Issued
- Issued on 9/20/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | SELLA BENYAMIN |
| Corrections Issued | 8/30/2022 | SELLA BENYAMIN |
| Quality Review Completed | 9/1/2022 | STEVEN KIM |
| Building Plans Picked Up | 9/2/2022 | APPLICANT |
| Plan Check Approved | 9/20/2022 | SELLA BENYAMIN |
| Issued | 9/20/2022 | APPLICANT |
| CofO in Progress | 3/22/2024 | MATTHEW NELSON |
| Permit Finaled | 4/3/2024 | RUBEN SALAS |
| CofO Issued | 4/3/2024 | RUBEN SALAS |
| Permit Finaled | 4/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/6/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 9/7/2022 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 9/20/2022 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 9/20/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/3/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 11/15/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 11/15/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2022 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2023 | Corrections Issued | MATTHEW NELSON |
| Pre-Inspection | 1/27/2023 | Approved | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 2/21/2023 | Partial Approval | MATTHEW NELSON |
| Wood Frame | 2/21/2023 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/2/2023 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 3/2/2023 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 3/2/2023 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 3/2/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/3/2023 | Approved | MATTHEW NELSON |
| Green Building Rough | 5/3/2023 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 5/11/2023 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 5/11/2023 | Partial Approval | MATTHEW NELSON |
| Sewer | 5/11/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 6/6/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 6/6/2023 | Approved | DAVID ANDERSON |
| Insulation | 6/27/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 7/5/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 7/5/2023 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 12/7/2023 | Approved | MATTHEW NELSON |
| HVAC-Final | 12/7/2023 | Approved | MATTHEW NELSON |
| Final | 1/26/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 1/26/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 1/26/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/26/2024 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 1/26/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 1/26/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 3/22/2024 | Approved | MATTHEW NELSON |
| Final | 3/22/2024 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 3/22/2024 | Approved | MATTHEW NELSON |