9752 W LA CANADA WAY 91040
Certificate Information: 9752 W LA CANADA WAY 91040
- Application / Permit
- 22010-20000-04180
- Plan Check / Job No.
- B22VN12766
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN new detached ADU 800 SF Max per State law GCS 65852.2(e)(1)(B) and LAMC 12.22 A33(c)(d)(g). NFPA-13 D Require. 1 parking for ADU require. See Comments. **************Total of 3 permits for ADU on the lot. 2 permits to be voided.****
- Permit Issued
- Issued on 10/5/2022
- Issuing Office
- Current Status
- CofO Issued on 12/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2022 | ZAW HAN |
| Corrections Issued | 8/27/2022 | ZAW HAN |
| Plan Check Approved | 10/5/2022 | ZAW HAN |
| Issued | 10/5/2022 | APPLICANT |
| CofO in Progress | 10/14/2023 | DAVID ANDERSON |
| Permit Finaled | 12/12/2023 | RUBEN SALAS |
| CofO Issued | 12/12/2023 | RUBEN SALAS |
| Permit Finaled | 12/12/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/29/2022 | ROMAN GUTIERREZ |
| BHO/Hillside ordinance | Cleared | 8/29/2022 | ROMAN GUTIERREZ |
| BHO/Hillside ordinance | Cleared | 8/29/2022 | ROMAN GUTIERREZ |
| BHO/Hillside ordinance | Cleared | 8/29/2022 | ROMAN GUTIERREZ |
| BHO/Hillside ordinance | Cleared | 8/29/2022 | ROMAN GUTIERREZ |
| BHO/Hillside ordinance | Cleared | 8/29/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 8/29/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2022 | ROMAN GUTIERREZ |
| Hydrant and Access approval | Cleared | 9/27/2022 | MATTHEW CRAIG |
| Miscellaneous | Cleared | 9/27/2022 | CECILIA CASTILLO |
| Miscellaneous | Cleared | 9/27/2022 | CECILIA CASTILLO |
| Specific Plan | Cleared | 9/27/2022 | CECILIA CASTILLO |
| Low Impact Development | Cleared | 9/28/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/29/2022 | ROMAN GUTIERREZ |
| GPI Written Notices | Cleared | 10/5/2022 | LANNY MERRICK |
| Grading Pre-Inspection | Cleared | 10/5/2022 | LANNY MERRICK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moradian,, Helbert; Lic. No.: C76618 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/25/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 2/1/2023 | Partial Approval | DAVID ANDERSON |
| Footing/Foundation/Slab | 2/14/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 3/16/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 3/16/2023 | Approved | DAVID ANDERSON |
| Special/Order Compliance | 3/16/2023 | Corrections Issued | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 3/16/2023 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 4/5/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 4/5/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 4/5/2023 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 4/5/2023 | Approved | DAVID ANDERSON |
| Insulation | 4/14/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 4/14/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 4/20/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 4/20/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Shower Pan | 4/20/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 5/15/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 7/6/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 9/14/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 9/14/2023 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 9/14/2023 | Approved | DAVID ANDERSON |
| HVAC-Final | 9/14/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 9/14/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 9/14/2023 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 9/14/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 9/14/2023 | Approved | DAVID ANDERSON |
| Final | 10/12/2023 | OK to Issue CofO | DAVID ANDERSON |
| Service/Power Release | 10/12/2023 | Approved | DAVID ANDERSON |