15952 W TUBA ST 91343
Certificate Information: 15952 W TUBA ST 91343
- Application / Permit
- 22010-20000-04173
- Plan Check / Job No.
- B22VN12743
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) [NFPA-13D FIRE SPRINKLERS THROUGHOUT]
- Permit Issued
- Issued on 8/15/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 8/30/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 9/1/2022 | STEVEN KIM |
| Building Plans Picked Up | 9/1/2022 | APPLICANT |
| Applicant returned to address corrections | 12/29/2022 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 1/24/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 2/23/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 6/27/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 7/25/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 8/10/2023 | NILOOFAR MEHRAIN |
| Issued | 8/15/2023 | APPLICANT |
| CofO in Progress | 2/6/2025 | JAVIER RAMOS JR |
| Permit Finaled | 2/20/2025 | RUBEN SALAS |
| CofO Issued | 2/20/2025 | RUBEN SALAS |
| Permit Finaled | 2/20/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/13/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2022 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 9/13/2022 | VASIL MIHALEV |
| Sewer availability | Cleared | 9/13/2022 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 10/9/2022 | RUEL COLE |
| Low Impact Development | Cleared | 12/28/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 12/28/2022 | COLIN LOREDO |
| Construction near power lines | Cleared | 1/18/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/18/2023 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 6/27/2023 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/11/2024 | Partial Approval | JAVIER RAMOS JR |
| Special/Order Compliance | 1/11/2024 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 1/16/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2024 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2024 | Partial Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2024 | Corrections Issued | JAVIER RAMOS JR |
| Pre-Inspection | 5/8/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/24/2024 | Approved | JAVIER RAMOS JR |
| Sewer | 8/6/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/21/2024 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/22/2024 | Approved | ROBERT GOLD |
| ELECTRICAL-Rough | 8/22/2024 | Approved | ROBERT GOLD |
| Green Building Rough | 8/22/2024 | Approved | ROBERT GOLD |
| HVAC-Rough | 8/22/2024 | Partial Approval | ROBERT GOLD |
| Insulation | 8/22/2024 | Partial Approval | LOUIS ESCOTO |
| Verify Sprinkler Sign Off | 8/22/2024 | Approved | ROBERT GOLD |
| Insulation | 8/26/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 8/29/2024 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 10/28/2024 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 1/15/2025 | Approved | JAVIER RAMOS JR |
| Final | 1/15/2025 | Corrections Issued | JAVIER RAMOS JR |
| Gas Test | 1/15/2025 | Approved | JAVIER RAMOS JR |
| Green Building Final | 1/15/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Final | 1/15/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 1/15/2025 | SGSOV Not Ready | JAVIER RAMOS JR |
| Smoke Detectors | 1/15/2025 | Approved | JAVIER RAMOS JR |
| Final | 1/24/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 1/24/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 1/24/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 1/24/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 1/24/2025 | Approved | JAVIER RAMOS JR |
| Final | 2/6/2025 | OK to Issue CofO | JAVIER RAMOS JR |