15952 W TUBA ST 91343

Certificate Information: 15952 W TUBA ST 91343

Application / Permit
22010-20000-04173
Plan Check / Job No.
B22VN12743
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) [NFPA-13D FIRE SPRINKLERS THROUGHOUT]
Permit Issued
Issued on 8/15/2023
Issuing Office
Valley
Current Status
CofO Issued on 2/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 NILOOFAR MEHRAIN
Corrections Issued 8/30/2022 NILOOFAR MEHRAIN
Quality Review Completed 9/1/2022 STEVEN KIM
Building Plans Picked Up 9/1/2022 APPLICANT
Applicant returned to address corrections 12/29/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 1/24/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 2/23/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/27/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 7/25/2023 NILOOFAR MEHRAIN
Plan Check Approved 8/10/2023 NILOOFAR MEHRAIN
Issued 8/15/2023 APPLICANT
CofO in Progress 2/6/2025 JAVIER RAMOS JR
Permit Finaled 2/20/2025 RUBEN SALAS
CofO Issued 2/20/2025 RUBEN SALAS
Permit Finaled 2/20/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/13/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/13/2022 LEE GUILBEAUX
Grading Pre-Inspection Cleared 9/13/2022 VASIL MIHALEV
Sewer availability Cleared 9/13/2022 LEE GUILBEAUX
Hydrant and Access approval Cleared 10/9/2022 RUEL COLE
Low Impact Development Cleared 12/28/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 12/28/2022 COLIN LOREDO
Construction near power lines Cleared 1/18/2023 RIDWAN HARDY
Construction within easement Cleared 1/18/2023 RIDWAN HARDY
GPI Written Notices Cleared 6/27/2023 NILOOFAR MEHRAIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/11/2024 Partial Approval JAVIER RAMOS JR
Special/Order Compliance 1/11/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 1/16/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/2/2024 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/21/2024 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/22/2024 Corrections Issued JAVIER RAMOS JR
Pre-Inspection 5/8/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/26/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 7/24/2024 Approved JAVIER RAMOS JR
Sewer 8/6/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/21/2024 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 8/22/2024 Approved ROBERT GOLD
ELECTRICAL-Rough 8/22/2024 Approved ROBERT GOLD
Green Building Rough 8/22/2024 Approved ROBERT GOLD
HVAC-Rough 8/22/2024 Partial Approval ROBERT GOLD
Insulation 8/22/2024 Partial Approval LOUIS ESCOTO
Verify Sprinkler Sign Off 8/22/2024 Approved ROBERT GOLD
Insulation 8/26/2024 Approved JAVIER RAMOS JR
Drywall Nailing 8/29/2024 Approved LOUIS ESCOTO
Interior/Exterior Lathing 10/28/2024 Approved WILLIAM WREN
ELECTRICAL-Final 1/15/2025 Approved JAVIER RAMOS JR
Final 1/15/2025 Corrections Issued JAVIER RAMOS JR
Gas Test 1/15/2025 Approved JAVIER RAMOS JR
Green Building Final 1/15/2025 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Final 1/15/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 1/15/2025 SGSOV Not Ready JAVIER RAMOS JR
Smoke Detectors 1/15/2025 Approved JAVIER RAMOS JR
Final 1/24/2025 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 1/24/2025 Approved JAVIER RAMOS JR
HVAC-Final 1/24/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 1/24/2025 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 1/24/2025 Approved JAVIER RAMOS JR
Final 2/6/2025 OK to Issue CofO JAVIER RAMOS JR