701 N TIGERTAIL ROAD 90049

Certificate Information: 701 N TIGERTAIL ROAD 90049

Application / Permit
22010-20000-04167
Plan Check / Job No.
B22VN08280
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 14'9" X 24'4" DETACHED ONE STORY RECREATION ROOM, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 3/22/2023
Issuing Office
Current Status
Issued on 3/22/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/27/2022 APPLICANT
Assigned to Plan Check Engineer 6/3/2022 COLIN LOREDO
Corrections Issued 7/18/2022 COLIN LOREDO
Applicant returned to address corrections 8/10/2022 RARES BODEA
Applicant returned to address corrections 8/19/2022 RARES BODEA
Applicant returned to address corrections 9/14/2022 RARES BODEA
Plan Check Approved 3/22/2023 RARES BODEA
Issued 3/22/2023 APPLICANT

Permit Application Clearance Information

Low Impact Development Cleared 8/26/2022 SUNG JOON WON
BHO/Hillside ordinance Cleared 8/29/2022 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 8/29/2022 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 8/29/2022 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 8/29/2022 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 8/29/2022 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 8/29/2022 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 9/7/2022 HISASHI KOBAYAKAWA
Distance to fire station Cleared 9/27/2022 MATTHEW CRAIG
Hydrant and Access approval Cleared 9/27/2022 MATTHEW CRAIG
GPI Written Notices Cleared 12/8/2022 RARES BODEA
Grading Pre-Inspection Cleared 12/8/2022 RARES BODEA

Contact Information

Contractor Building Solutions And Design; Lic. No.: 940604-B 860 VIA DE LA PAZ SUITE D3E      PACIFIC PALISADES, CA 90272
Engineer Cox,, Steven Jeffrey; Lic. No.: C48940 130 MAGELLAN ST      THOUSAND OAKS, CA 91360

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/10/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 4/11/2023 Conditional Approval CARLOS MATAMOROS
Deputy Shotcrete 5/1/2023 Approved KEVIN SARGSYAN
Deputy Shotcrete 5/2/2023 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 5/2/2023 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 6/26/2023 Approved KENNETH NAGLE
Footing/Foundation/Slab 7/14/2023 Partial Approval KEVIN SARGSYAN
Deputy Other (see comments) 7/18/2023 Approved KEVIN SARGSYAN
PLUMBING-Rough 4/24/2024 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 4/29/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 5/14/2024 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 5/22/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 7/8/2024 Approved KEVIN SARGSYAN
HVAC-Rough 7/9/2024 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 7/12/2024 Partial Approval KEVIN SARGSYAN
HVAC-Rough 7/12/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 7/24/2024 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 10/1/2024 Partial Approval STEPHANIE SWANSON
BUILDING-Rough-Frame 2/24/2025 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 4/7/2025 Not Ready for Inspection KEVIN SARGSYAN
Verify Sprinkler Sign Off 4/7/2025 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 4/9/2025 Partial Approval KEVIN SARGSYAN
Green Building Rough 4/9/2025 Partial Approval KEVIN SARGSYAN
Interior/Exterior Lathing 4/9/2025 Partial Approval KEVIN SARGSYAN
Insulation 8/7/2025 Partial Approval KEVIN SARGSYAN
Insulation 8/13/2025 Approved BOBBY KEY
Drywall Nailing 8/19/2025 Conditional Approval STEPHANIE SWANSON
Green Building Rough 8/19/2025 Not Ready for Inspection STEPHANIE SWANSON
Interior/Exterior Lathing 8/26/2025 Partial Approval KEVIN SARGSYAN