946 N KENFIELD AVE 90049
Certificate Information: 946 N KENFIELD AVE 90049
- Application / Permit
- 22010-20000-04138
- Plan Check / Job No.
- B22VN12641
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 22'-3" X 43'-11" IRREGULAR SHAPED 1-STORY ACCESSORY DWELLING UNIT PER GC 66323(a)(2) OVER BASEMENT REC ROOM. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/27/2025
- Issuing Office
- Valley
- Current Status
- Issued on 6/27/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2022 | RAPHAEL ROSAS |
| Corrections Issued | 9/14/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 9/23/2022 | STEVEN KIM |
| Building Plans Picked Up | 9/29/2022 | APPLICANT |
| Applicant returned to address corrections | 11/17/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/27/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 9/13/2023 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 10/3/2023 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 4/3/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 11/13/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 6/24/2025 | RAPHAEL ROSAS |
| Issued | 6/27/2025 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/11/2023 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 10/11/2023 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 10/11/2023 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 10/11/2023 | BRENDEN HAWK |
| Address approval | Cleared | 10/12/2023 | BRENDEN HAWK |
| Distance to fire station | Cleared | 10/12/2023 | LAVEON RIDER |
| Hydrant and Access approval | Cleared | 10/12/2023 | LAVEON RIDER |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2023 | DINAH GARIN |
| Sewer availability | Cleared | 10/20/2023 | DINAH GARIN |
| GPI Written Notices | Cleared | 11/13/2024 | RAPHAEL ROSAS |
| Low Impact Development | Cleared | 2/6/2025 | ERNEST TSE |
| BHO/Hillside ordinance | Cleared | 4/30/2025 | KIMBERLY HERNANDEZ |
| Drainage to Storm Drain | Cleared | 6/20/2025 | VLADIMIR ARUTYUNYAN |
| Roof/Waste drainage to street | Cleared | 6/20/2025 | VLADIMIR ARUTYUNYAN |
| Grading Pre-Inspection | Cleared | 6/23/2025 | RAPHAEL ROSAS |
Contact Information
| Architect | Farhad,, Farshid; Lic. No.: C19859 | 840 20TH ST. # 13 SANTA MONICA, CA 90403 |
| Contractor | H W Holmes Inc; Lic. No.: 945923-B | P O BOX 2302 CAMARILLO, CA 930112302 |
| Engineer | Judd,, Shane Dennis; Lic. No.: C70991 | 17 E HIGH ST STE A MOORPARK, CA 93021 |
| Engineer | Minas,, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
| Geologist | Minas,, Shant; Lic. No.: EG2607 | 566 RIVERDALE DRIVE GLENDALE, CA 91204 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/4/2025 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 4/8/2026 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 5/6/2026 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 5/14/2026 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2026 | Partial Approval | DAVID SCANTLIN |