8520 N DE CELIS PL 91343
Certificate Information: 8520 N DE CELIS PL 91343
- Application / Permit
- 22010-20000-04121
- Plan Check / Job No.
- B22VN12605
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DET. ADU W/ATT. GARAGE per City Ordinance. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 10/20/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2022 | SERGIO MUNIZ |
| Corrections Issued | 8/27/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 9/26/2022 | APPLICANT |
| Plan Check Approved | 10/19/2022 | RICARDO RAMIREZ |
| Issued | 10/20/2022 | APPLICANT |
| CofO in Progress | 1/18/2024 | RAUL OLAGI |
| Permit Finaled | 4/2/2024 | RUBEN SALAS |
| CofO Issued | 4/2/2024 | RUBEN SALAS |
| Permit Finaled | 4/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Tract Map conditions | Cleared | 9/27/2022 | ASHLEY RODARTE |
| Address approval | Cleared | 9/28/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/28/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 10/17/2022 | CARLOS AGUILERA |
| Hold | Cleared | 11/15/2022 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/21/2022 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 11/30/2022 | Approved | RAUL OLAGI |
| Deputy Drilled-In Anchors | 12/29/2022 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 12/29/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 12/29/2022 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Rough | 12/29/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/29/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/9/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 1/9/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/18/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Rough | 1/18/2023 | Not Ready for Inspection | RAUL OLAGI |
| Verify Sprinkler Sign Off | 1/18/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/23/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/30/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 1/30/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 1/30/2023 | Partial Approval | RAUL OLAGI |
| Insulation | 2/3/2023 | Approved | RAUL OLAGI |
| Shower Pan | 2/3/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 2/13/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 3/28/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 3/28/2023 | Partial Approval | RAUL OLAGI |
| Sewer | 4/11/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 4/14/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 4/25/2023 | Corrections Issued | RAUL OLAGI |
| Final | 4/25/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 4/25/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 4/25/2023 | Corrections Issued | RAUL OLAGI |
| Smoke Detectors | 4/25/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 5/24/2023 | Approved | RAUL OLAGI |
| Final | 5/24/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 5/24/2023 | Approved | RAUL OLAGI |
| HVAC-Final | 5/24/2023 | Approved | RAUL OLAGI |
| PLUMBING-Final | 5/24/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 5/24/2023 | SGSOV Approved | RAUL OLAGI |
| Special/Order Compliance | 12/5/2023 | Corrections Issued | RAUL OLAGI |
| Final | 1/18/2024 | OK to Issue CofO | RAUL OLAGI |
| Service/Power Release | 1/18/2024 | Approved | RAUL OLAGI |