820-820 1/2 W 42ND PL 90037
Certificate Information: 820-820 1/2 W 42ND PL 90037
- Application / Permit
- 22010-20000-04119
- Plan Check / Job No.
- B22VN12598
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 1-STORY 2-UNIT ACCESSORY DWELLING UNIT CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 2/28/2023
- Issuing Office
- Current Status
- CofO Issued on 3/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2022 | DANIEL YIP |
| Corrections Issued | 9/3/2022 | DANIEL YIP |
| Quality Review Completed | 9/6/2022 | GARO TELMI |
| Plan Check Approved | 12/28/2022 | DANIEL YIP |
| Issued | 2/28/2023 | APPLICANT |
| CofO in Progress | 3/12/2024 | SABAS ALONSO |
| CofO Issued | 3/18/2024 | DEROLD HAUFF |
| Permit Finaled | 3/18/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/18/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 10/19/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 12/2/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/9/2022 | THAN WIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/10/2023 | Partial Approval | SABAS ALONSO |
| Sewer | 4/10/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 4/10/2023 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 4/24/2023 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 4/24/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/2/2023 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 6/2/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 6/2/2023 | Approved | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 6/7/2023 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 6/12/2023 | Approved | STUART CHAPMAN |
| HVAC-Rough | 6/12/2023 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 6/12/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Rough | 6/15/2023 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 6/15/2023 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 6/15/2023 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/20/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 6/20/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 6/20/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 6/20/2023 | Approved | SABAS ALONSO |
| Insulation | 6/23/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 6/30/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 10/16/2023 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 10/20/2023 | Approved | JUSTIN HAWLEY |
| Final | 2/7/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 2/7/2024 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 2/7/2024 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 2/7/2024 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 2/7/2024 | Approved | SABAS ALONSO |
| Final | 2/22/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 2/22/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 2/22/2024 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 2/22/2024 | Approved | SABAS ALONSO |
| Final | 3/11/2024 | OK to Issue CofO | SABAS ALONSO |