13256 W STAGG ST 91605
Certificate Information: 13256 W STAGG ST 91605
- Application / Permit
- 22010-20000-04077
- Plan Check / Job No.
- B22VN12477
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- IRREG. SHAPED 34'-0" x 12'-7" NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
- Permit Issued
- Issued on 8/11/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2022 | JESSE ARELLANO |
| Corrections Issued | 8/25/2022 | JESSE ARELLANO |
| Building Plans Picked Up | 8/26/2022 | APPLICANT |
| Applicant returned to address corrections | 6/27/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 6/28/2023 | GIOVANNY CHAVEZ |
| Issued | 8/11/2023 | APPLICANT |
| CofO in Progress | 7/31/2025 | VINCENT HANLEY |
| Permit Finaled | 8/19/2025 | RUBEN SALAS |
| CofO Issued | 8/19/2025 | RUBEN SALAS |
| Permit Finaled | 8/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/20/2022 | COLIN LOREDO |
| Construction near power lines | Cleared | 12/19/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/19/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 1/30/2023 | ROGELIO CORTES |
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 5/1/2023 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 6/27/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/18/2023 | Approved | GREGG CUMMINGS |
| Sewer | 12/14/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Underground Mechanical | 12/14/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 12/18/2023 | Partial Approval | GREGG CUMMINGS |
| Sewer | 12/18/2023 | Approved | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 12/28/2023 | Partial Approval | JOHN COLEMAN |
| Footing/Foundation/Slab | 12/28/2023 | Corrections Issued | JOHN COLEMAN |
| PLUMBING-Rough | 12/28/2023 | Partial Approval | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 1/3/2024 | Approved | JOHN COLEMAN |
| ELECTRICAL-Rough | 1/30/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2024 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 1/30/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 2/20/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2024 | Partial Approval | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 2/20/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 2/28/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 3/1/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 3/1/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 3/1/2024 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 3/1/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 3/4/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 3/4/2024 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 3/4/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 3/11/2024 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 3/11/2024 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 3/28/2024 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 3/28/2024 | Approved | GREGG CUMMINGS |
| Insulation | 3/28/2024 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 4/2/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 4/8/2024 | Partial Approval | GREGG CUMMINGS |
| Final | 12/6/2024 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 12/6/2024 | Approved | VINCENT HANLEY |
| Green Building Final | 12/6/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 12/6/2024 | SGSOV Not Ready | VINCENT HANLEY |
| Service/Power Release | 12/6/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Smoke Detectors | 12/6/2024 | Approved | VINCENT HANLEY |
| Pre-Inspection | 2/5/2025 | Corrections Issued | JACK KARGODORIAN |
| Final | 4/3/2025 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 4/3/2025 | SGSOV Not Ready | VINCENT HANLEY |
| Service/Power Release | 4/3/2025 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Final | 7/8/2025 | Approved | VINCENT HANLEY |
| Final | 7/8/2025 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 7/8/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 7/8/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/8/2025 | SGSOV Not Required | VINCENT HANLEY |
| Service/Power Release | 7/8/2025 | Approved | VINCENT HANLEY |
| Final | 7/31/2025 | OK to Issue CofO | VINCENT HANLEY |