6105 N GOODLAND AVE 91606
Certificate Information: 6105 N GOODLAND AVE 91606
- Application / Permit
- 22010-20000-04076
- Plan Check / Job No.
- B22VN12474
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and remodel of (E) SFD
- Permit Issued
- Issued on 9/28/2022
- Issuing Office
- Current Status
- CofO Issued on 11/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2022 | SHANGQIN XIE |
| Corrections Issued | 8/20/2022 | SHANGQIN XIE |
| Plan Check Approved | 9/1/2022 | RAHEL BEYENE |
| Issued | 9/28/2022 | APPLICANT |
| CofO in Progress | 4/16/2024 | JUAN VALENZUELA |
| Permit Finaled | 11/19/2024 | DANIEL ORRANTE |
| CofO Issued | 11/19/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/19/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/23/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 8/24/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 8/24/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 8/24/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 8/24/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manlangit,, Vicente; Lic. No.: C75499 | 20832 VALERIO ST UNIT 14 WINNETKA, CA 91306 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/1/2023 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 2/6/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/2/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/2/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/6/2023 | Not Ready for Inspection | KIRK SANDERS |
| Pre-Inspection | 3/6/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2023 | Partial Approval | JOHN COLEMAN |
| PLUMBING-Rough | 3/16/2023 | Corrections Issued | JOHN COLEMAN |
| Insulation | 3/24/2023 | Partial Approval | KIRK SANDERS |
| Underground Mechanical | 3/24/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/30/2023 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 3/30/2023 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2023 | Partial Approval | KIRK SANDERS |
| HVAC-Rough | 3/30/2023 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 3/30/2023 | Partial Approval | KIRK SANDERS |
| Drywall Nailing | 4/11/2023 | Partial Approval | ROBERT GOLD |
| Shower Pan | 4/11/2023 | Partial Approval | ROBERT GOLD |
| Interior/Exterior Lathing | 4/13/2023 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/28/2023 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 4/28/2023 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/10/2023 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 5/10/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 5/10/2023 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 5/10/2023 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/17/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 5/17/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 5/17/2023 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 5/17/2023 | Approved | KIRK SANDERS |
| Insulation | 5/22/2023 | Approved | KIRK SANDERS |
| Shower Pan | 5/22/2023 | Not Ready for Inspection | KIRK SANDERS |
| Drywall Nailing | 5/24/2023 | Approved | KIRK SANDERS |
| Shower Pan | 5/24/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 6/14/2023 | Approved | KIRK SANDERS |
| Final | 9/6/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 9/6/2023 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/6/2023 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 9/6/2023 | Approved | KIRK SANDERS |
| Final | 2/12/2024 | Not Ready for Inspection | JOSE AVILA |
| Final | 3/6/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 3/6/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 3/6/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Final | 4/15/2024 | OK to Issue CofO | JUAN VALENZUELA |
| Green Building Final | 4/15/2024 | Approved | JUAN VALENZUELA |