21620 W LOS ALIMOS ST 91311

Certificate Information: 21620 W LOS ALIMOS ST 91311

Application / Permit
22010-20000-04064
Plan Check / Job No.
B22VN12442
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW IRREGULAR 21'6" x 62'11" SINGLE-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d)
Permit Issued
Issued on 11/8/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 LUIS RINCON
Corrections Issued 8/25/2022 LUIS RINCON
Building Plans Picked Up 8/31/2022 APPLICANT
Plan Check Approved 11/8/2022 SERGIO MUNIZ
Issued 11/8/2022 APPLICANT
CofO in Progress 2/4/2025 JEFFREY PARD
Permit Finaled 4/2/2025 JOHN JANSON
CofO Issued 4/2/2025 JOHN JANSON
Permit Finaled 4/2/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/6/2022 MEGAN GODINEZ
Sewer availability Cleared 9/6/2022 MEGAN GODINEZ
Hydrant and Access approval Cleared 10/7/2022 RUEL COLE
Low Impact Development Cleared 10/31/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 10/31/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 11/1/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Hajdari,, Genti; Lic. No.: C88031 140 S MENTOR AVE APT #207      PASADENA, CA 91106

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/3/2023 Corrections Issued HORACE FULTZ
Footing/Foundation/Slab 8/8/2023 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/20/2023 Approved JEFFREY PARD
ELECTRICAL-Rough 11/2/2023 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Corrections Issued STEVEN BACK
HVAC-Rough 11/2/2023 Corrections Issued STEVEN BACK
PLUMBING-Rough 11/2/2023 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 12/1/2023 Approved STEVEN BACK
HVAC-Rough 12/1/2023 Approved STEVEN BACK
PLUMBING-Rough 12/1/2023 Approved STEVEN BACK
BUILDING-Rough-Frame 12/8/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 12/8/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 12/8/2023 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 1/18/2024 Approved JEFFREY PARD
Green Building Rough 1/18/2024 Not Ready for Inspection JEFFREY PARD
Green Building Rough 1/25/2024 No Access for Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 1/25/2024 No Access for Inspection KRISTEN CAUSEY
Green Building Rough 1/29/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 1/29/2024 Partial Approval DAVID SCANTLIN
Insulation 2/6/2024 Approved HENRY KIM
Drywall Nailing 2/13/2024 Approved JEFFREY PARD
Interior/Exterior Lathing 3/20/2024 Approved JEFFREY PARD
PLUMBING-Rough 3/20/2024 Approved JEFFREY PARD
Sewer 3/20/2024 Approved JEFFREY PARD
ELECTRICAL-Final 6/3/2024 Corrections Issued JEFFREY PARD
ELECTRICAL-Final 6/7/2024 Approved JEFFREY PARD
PLUMBING-Final 6/28/2024 Approved JEFFREY PARD
Service/Power Release 7/30/2024 Approved JEFFREY PARD
Final 9/24/2024 Not Ready for Inspection JEFFREY PARD
Green Building Final 9/24/2024 Not Ready for Inspection JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 9/24/2024 SGSOV Not Required JEFFREY PARD
Smoke Detectors 9/24/2024 Approved JEFFREY PARD
Final 12/9/2024 Corrections Issued JEFFREY PARD
Green Building Final 12/9/2024 Corrections Issued JEFFREY PARD
Service/Power Release 12/9/2024 Approved JEFFREY PARD
Final 2/3/2025 OK to Issue CofO JEFFREY PARD
Green Building Final 2/3/2025 Approved JEFFREY PARD