232 E GAGE AVE UNIT C 90003
Certificate Information: 232 E GAGE AVE UNIT C 90003
- Application / Permit
- 22010-20000-04049
- Plan Check / Job No.
- B22VN11906
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached 2-Story ADU AT REAR OF LOT.
- Permit Issued
- Issued on 4/17/2023
- Issuing Office
- Current Status
- CofO Issued on 12/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2022 | JOE VO |
| Corrections Issued | 8/13/2022 | JOE VO |
| Quality Review Completed | 8/15/2022 | GARO TELMI |
| Plan Check Approved | 3/24/2023 | JOE VO |
| Issued | 4/17/2023 | APPLICANT |
| CofO in Progress | 12/8/2023 | MICHAEL LEWIS |
| CofO Issued | 12/14/2023 | DEROLD HAUFF |
| Permit Finaled | 12/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/13/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2022 | WALLIE JONG |
| Sewer availability | Cleared | 10/21/2022 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 11/5/2022 | RUEL COLE |
| Low Impact Development | Cleared | 12/21/2022 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 12/21/2022 | WALLIE JONG |
| Construction near power lines | Cleared | 1/19/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Lajoma Construction Inc; Lic. No.: 864461-B | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/11/2023 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 5/18/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 5/18/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2023 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2023 | Partial Approval | STUART CHAPMAN |
| Deputy Wood Construction | 7/28/2023 | Approved | DONALD CRICHLOW |
| ELECTRICAL-Rough | 8/2/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 8/2/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 8/4/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 8/4/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 8/4/2023 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 8/4/2023 | Approved | MICHAEL LEWIS |
| Pre-Inspection | 8/7/2023 | Approved | MICHAEL LEWIS |
| Insulation | 8/9/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 8/14/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 8/14/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/20/2023 | Approved | MICHAEL LEWIS |
| Green Building Final | 11/20/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 11/20/2023 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 11/20/2023 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 11/20/2023 | Approved | MICHAEL LEWIS |
| HVAC-Final | 11/21/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 11/21/2023 | Approved | MICHAEL LEWIS |
| Final | 12/7/2023 | OK to Issue CofO | MICHAEL LEWIS |