232 E GAGE AVE UNIT C 90003

Certificate Information: 232 E GAGE AVE UNIT C 90003

Application / Permit
22010-20000-04049
Plan Check / Job No.
B22VN11906
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached 2-Story ADU AT REAR OF LOT.
Permit Issued
Issued on 4/17/2023
Issuing Office
Current Status
CofO Issued on 12/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/3/2022 APPLICANT
Assigned to Plan Check Engineer 8/12/2022 JOE VO
Corrections Issued 8/13/2022 JOE VO
Quality Review Completed 8/15/2022 GARO TELMI
Plan Check Approved 3/24/2023 JOE VO
Issued 4/17/2023 APPLICANT
CofO in Progress 12/8/2023 MICHAEL LEWIS
CofO Issued 12/14/2023 DEROLD HAUFF
Permit Finaled 12/14/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/13/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/20/2022 WALLIE JONG
Sewer availability Cleared 10/21/2022 WALLIE JONG
Hydrant and Access approval Cleared 11/5/2022 RUEL COLE
Low Impact Development Cleared 12/21/2022 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 12/21/2022 WALLIE JONG
Construction near power lines Cleared 1/19/2023 RIDWAN HARDY

Contact Information

Contractor Lajoma Construction Inc; Lic. No.: 864461-B       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/11/2023 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 5/18/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 5/18/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 6/6/2023 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/9/2023 Partial Approval STUART CHAPMAN
Deputy Wood Construction 7/28/2023 Approved DONALD CRICHLOW
ELECTRICAL-Rough 8/2/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 8/2/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 8/4/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 8/4/2023 Approved MICHAEL LEWIS
Green Building Rough 8/4/2023 Approved MICHAEL LEWIS
HVAC-Rough 8/4/2023 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 8/4/2023 Approved MICHAEL LEWIS
Pre-Inspection 8/7/2023 Approved MICHAEL LEWIS
Insulation 8/9/2023 Approved MICHAEL LEWIS
Drywall Nailing 8/14/2023 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 8/14/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/20/2023 Approved MICHAEL LEWIS
Green Building Final 11/20/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 11/20/2023 SGSOV Approved MICHAEL LEWIS
Service/Power Release 11/20/2023 Approved MICHAEL LEWIS
Smoke Detectors 11/20/2023 Approved MICHAEL LEWIS
HVAC-Final 11/21/2023 Approved MICHAEL LEWIS
PLUMBING-Final 11/21/2023 Approved MICHAEL LEWIS
Final 12/7/2023 OK to Issue CofO MICHAEL LEWIS