18817 W EDLEEN DR 91356
Certificate Information: 18817 W EDLEEN DR 91356
- Application / Permit
- 22010-20000-04043
- Plan Check / Job No.
- B22VN12399
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1) New 2 story sfd with basement and roof top deck. 2) Grading 3) Swimming pool & deck
- Permit Issued
- Issued on 8/16/2023
- Issuing Office
- Current Status
- Issued on 8/16/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | JOE VO |
| Corrections Issued | 8/20/2022 | JOE VO |
| Quality Review Completed | 8/22/2022 | GARO TELMI |
| Applicant returned to address corrections | 4/3/2023 | JOE VO |
| Plan Check Approved | 7/23/2023 | JOE VO |
| Issued | 8/16/2023 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 9/6/2022 | COLIN LOREDO |
| BHO/Hillside ordinance | Cleared | 9/6/2022 | COLIN LOREDO |
| BHO/Hillside ordinance | Cleared | 9/6/2022 | COLIN LOREDO |
| BHO/Hillside ordinance | Cleared | 9/6/2022 | COLIN LOREDO |
| BHO/Hillside ordinance | Cleared | 9/6/2022 | COLIN LOREDO |
| Permit | Cleared | 9/6/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 9/6/2022 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 10/17/2022 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2022 | ROSE MARIE SMITH |
| Low Impact Development | Cleared | 1/23/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/23/2023 | DAGOVERTO GUERRERO |
| Excavation more than 5-ft deep | Cleared | 3/30/2023 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
| Engineer | Lin,, Chi Hsin; Lic. No.: GE2921 | 123 N VALENCIA ST ALHAMBRA, CA 91801 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 8/7/2024 | Partial Approval | JOHN KIDWELL |
| Piling/Pier/Caisson | 10/2/2024 | Corrections Issued | JOHN KIDWELL |
| Green Building Rough | 11/5/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Reinforced Concrete Frame | 11/5/2024 | Partial Approval | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 11/5/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 11/26/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Reinforced Concrete Frame | 11/26/2024 | Partial Approval | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 11/26/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Deputy Reinf. Concrete | 11/27/2024 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 2/18/2025 | Partial Approval | JOHN KIDWELL |
| Underground Mechanical | 2/18/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Deputy Reinf. Concrete | 3/4/2025 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 3/21/2025 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2025 | Conditional Approval | JOHN KIDWELL |
| HVAC-Rough | 6/27/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2025 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 8/7/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 8/7/2025 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 8/19/2025 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2025 | Partial Approval | JOHN KIDWELL |
| HVAC-Rough | 8/19/2025 | Partial Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 8/19/2025 | Conditional Approval | JOHN KIDWELL |
| HVAC-Rough | 9/9/2025 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 9/9/2025 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 9/19/2025 | Approved | JOHN KIDWELL |
| Green Building Rough | 9/19/2025 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 9/19/2025 | Approved | JOHN KIDWELL |
| Insulation | 10/9/2025 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 10/9/2025 | Approved | JOHN KIDWELL |
| Drywall Nailing | 10/31/2025 | Approved | JOHN KIDWELL |
| Service/Power Release | 4/21/2026 | Approved | JOHN KIDWELL |
| HVAC-Final | 5/26/2026 | Partial Inspection | JOHN KIDWELL |