23312 W COHASSET ST 91304

Certificate Information: 23312 W COHASSET ST 91304

Application / Permit
22010-20000-04005
Plan Check / Job No.
B22VN12311
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORYSFD W/ ATTACHED GARAGE PER SB9 TW0-UNIT DEVELOPMENT CA GOVT CODE 65852.21 [NFPA-13D FIRE SPRINKLERS THROUGHOUT] **ePlan**
Permit Issued
Issued on 2/8/2023
Issuing Office
Current Status
CofO Issued on 10/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/11/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 NILOOFAR MEHRAIN
Corrections Issued 9/6/2022 NILOOFAR MEHRAIN
Quality Review Completed 9/13/2022 STEVEN KIM
Applicant returned to address corrections 12/14/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 1/11/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 1/30/2023 NILOOFAR MEHRAIN
Plan Check Approved 2/2/2023 NILOOFAR MEHRAIN
Issued 2/8/2023 APPLICANT
CofO in Progress 10/24/2023 CHRIS CHRISTENSEN
Permit Finaled 10/30/2023 JOHN JANSON
CofO Issued 10/30/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/13/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/14/2022 LEE GUILBEAUX
Sewer availability Cleared 9/14/2022 LEE GUILBEAUX
Grading Pre-Inspection Cleared 10/6/2022 ROBERT HUGHES
Senate Bill 9 Cleared 10/27/2022 DANG NGUYEN
Low Impact Development Cleared 11/10/2022 DEBORA LEITE
Hydrant and Access approval Cleared 11/14/2022 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 11/21/2022 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 11/21/2022 LEE GUILBEAUX
GPI Written Notices Cleared 1/30/2023 NILOOFAR MEHRAIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/3/2023 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 4/3/2023 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/13/2023 Approved CHRIS CHRISTENSEN
Underground Mechanical 4/13/2023 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/9/2023 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/15/2023 Conditional Approval CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 6/13/2023 Approved HORACE FULTZ
BUILDING-Rough-Frame 6/15/2023 Conditional Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 6/15/2023 Conditional Approval CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 6/15/2023 Approved CHRIS CHRISTENSEN
Deputy Wood Construction 6/16/2023 Conditional Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/21/2023 Partial Approval MORRIS JACKSON
BUILDING-Rough-Frame 6/26/2023 Approved CHRIS CHRISTENSEN
Green Building Rough 6/26/2023 Approved CHRIS CHRISTENSEN
Insulation 6/26/2023 Conditional Approval CHRIS CHRISTENSEN
Drywall Nailing 6/29/2023 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/29/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Shower Pan 6/29/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Interior/Exterior Lathing 7/5/2023 Partial Approval CHRIS CHRISTENSEN
Shower Pan 7/5/2023 Approved CHRIS CHRISTENSEN
Sewer 7/24/2023 Approved HORACE FULTZ
Underground Mechanical 7/24/2023 Approved HORACE FULTZ
ELECTRICAL-Final 9/21/2023 Approved CHRIS CHRISTENSEN
Final 9/21/2023 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 9/21/2023 Approved CHRIS CHRISTENSEN
PLUMBING-Final 9/21/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/21/2023 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 9/21/2023 Approved CHRIS CHRISTENSEN
Smoke Detectors 9/21/2023 Approved CHRIS CHRISTENSEN
Final 9/27/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Final 10/4/2023 Corrections Issued CHRIS CHRISTENSEN
Final 10/17/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Final 10/23/2023 OK to Issue CofO CHRIS CHRISTENSEN