7732-7734 N FULTON AVE 91605

Certificate Information: 7732-7734 N FULTON AVE 91605

Application / Permit
22010-20000-04001
Plan Check / Job No.
B22VN12293
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 39'-4" X 55'-10" TWO STORY WITH SINGLE FAMILY DWELLING PER SB9 Two-Unit Development Ca Govt Code 65852.21 WITH ATTACHED PATIO COVER ON FIRST FLOOR AND ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) ON SECOND FLOOR ALL WORK PER ENGINEERING NFPA 13R REQUIRED THROUGHOUT
Permit Issued
Issued on 2/22/2024
Issuing Office
Valley
Current Status
Issued on 2/22/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/10/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 8/30/2022 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 9/12/2022 OMID HEDAYAT
Building Plans Picked Up 9/13/2022 APPLICANT
Applicant returned to address corrections 2/7/2023 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 2/14/2023 SEWADA ZADOORAN MILAGARDI
Issued 2/22/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/19/2022 MEGAN GODINEZ
Senate Bill 9 Cleared 12/20/2022 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 12/22/2022 MEGAN GODINEZ
Sewer availability Cleared 12/22/2022 MEGAN GODINEZ
Low Impact Development Cleared 1/23/2023 ERNEST TSE
Hydrant and Access approval Cleared 1/24/2023 KURT CORRAL
Roof/Waste drainage to street Cleared 1/24/2023 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/18/2024 Approved CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 4/2/2024 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 4/2/2024 Not Ready for Inspection GREGG CUMMINGS
Footing/Foundation/Slab 5/2/2024 Not Ready for Inspection GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 7/17/2024 Approved GREGG CUMMINGS
Footing/Foundation/Slab 7/17/2024 Approved GREGG CUMMINGS
Special/Order Compliance 7/17/2024 Corrections Issued GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 8/19/2024 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 8/30/2024 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/13/2024 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 11/1/2024 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 11/1/2024 Not Ready for Inspection GREGG CUMMINGS
Green Building Rough 11/1/2024 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 11/1/2024 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 11/1/2024 Approved GREGG CUMMINGS
Verify Sprinkler Sign Off 11/1/2024 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 11/6/2024 Corrections Issued GREGG CUMMINGS
HVAC-Rough 11/6/2024 Approved GREGG CUMMINGS
ELECTRICAL-Rough 11/13/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Partial Approval VINCENT HANLEY
Shower Pan 11/13/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 12/4/2024 Corrections Issued VINCENT HANLEY
Green Building Rough 12/4/2024 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 12/4/2024 Corrections Issued VINCENT HANLEY
Sewer 12/23/2024 Approved DAVID MATSON
Underground Mechanical 12/23/2024 Partial Approval DAVID MATSON
ELECTRICAL-Rough 12/26/2024 Approved KEVIN BERBERYAN
Underground Mechanical 12/26/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 2/25/2025 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 2/25/2025 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 2/25/2025 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 3/4/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/4/2025 Partial Approval VINCENT HANLEY
Verify Sprinkler Sign Off 3/4/2025 Approved VINCENT HANLEY
Insulation 3/7/2025 Approved LOUIS ESCOTO
Drywall Nailing 3/11/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 3/14/2025 Approved LOUIS ESCOTO
Final 4/30/2025 Corrections Issued VINCENT HANLEY
Green Building Final 4/30/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/30/2025 SGSOV Not Required VINCENT HANLEY
Service/Power Release 4/30/2025 Not Ready for Inspection VINCENT HANLEY
Smoke Detectors 4/30/2025 Approved VINCENT HANLEY