4074 S EAST BLVD 90066
Certificate Information: 4074 S EAST BLVD 90066
- Application / Permit
- 22010-20000-03997
- Plan Check / Job No.
- B22VN12271
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 32'-2" x 36'-4" TWO STORY DET. ACC. BLDG; 1ST FLR TO BE 2-CAR GARAGE W/ STORAGE AREA AND A LAUNDRY ROOM/BATHROOM AND ADU ENTERANCE/CLOSET, 2ND FLR TO BE ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 5/5/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | SEAN SHAHMIRI |
| Corrections Issued | 8/22/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 8/24/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 8/26/2022 | APPLICANT |
| Plan Check Approved | 4/27/2023 | SEAN SHAHMIRI |
| Issued | 5/5/2023 | APPLICANT |
| CofO in Progress | 12/30/2024 | JESUS PINEDA |
| Permit Finaled | 12/31/2024 | RICHARD STEINBACH |
| CofO Issued | 12/31/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/31/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 10/12/2022 | AHMED AMARRAGY |
| Construction near power lines | Cleared | 1/25/2023 | RIDWAN HARDY |
| ZA Case | Cleared | 3/28/2023 | NELSON RODRIGUEZ |
| Hydrant and Access approval | Cleared | 3/31/2023 | LAVEON RIDER |
| Roof/Waste drainage to street | Cleared | 4/12/2023 | AHMED AMARRAGY |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2023 | DARIN LAM |
| Specific Plan | Cleared | 4/20/2023 | PEDRO AYALA |
| Sewer availability | Cleared | 4/22/2023 | KEVIN AVILA |
| Low Impact Development | Cleared | 4/27/2023 | SARAH YOUSSEF |
Contact Information
| Contractor | Mp Builder; Lic. No.: 1092835-B | 1843 10TH STREET #6 SANTA MONICA, CA 90404 |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 9/6/2023 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 9/6/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Special/Order Compliance | 9/6/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2023 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2023 | Partial Inspection | JESUS RODRIGUEZ |
| Special/Order Compliance | 11/8/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Gas Test | 11/16/2023 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 11/28/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 11/28/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 11/28/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 12/18/2023 | Approved | BOBBY KEY |
| Green Building Rough | 12/18/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 12/18/2023 | Approved | BOBBY KEY |
| Verify Sprinkler Sign Off | 12/18/2023 | Approved | BOBBY KEY |
| Insulation | 1/4/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Insulation | 1/12/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 1/30/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 1/30/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 3/27/2024 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 3/27/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 7/12/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Final | 7/12/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 8/1/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 8/1/2024 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 8/1/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 9/6/2024 | Approved | TEMISTOCLES CAAL |
| Final | 11/15/2024 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 11/15/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 11/15/2024 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 11/15/2024 | Approved | HERBERT GIRON |
| Special/Order Compliance | 11/15/2024 | Partial Inspection | TEMISTOCLES CAAL |
| Final | 12/27/2024 | OK to Issue CofO | JESUS PINEDA |
| Footing/Foundation/Slab | 12/27/2024 | Approved | JESUS PINEDA |