19131 W LEMAY ST 91335
Certificate Information: 19131 W LEMAY ST 91335
- Application / Permit
- 22010-20000-03991
- Plan Check / Job No.
- B22VN12255
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan New Detached ADU , 633 SF
- Permit Issued
- Issued on 12/1/2022
- Issuing Office
- Current Status
- CofO Issued on 5/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2022 | MINA HABILI |
| Corrections Issued | 8/18/2022 | MINA HABILI |
| Applicant returned to address corrections | 11/15/2022 | JOSEPH RAFOLS |
| Plan Check Approved | 11/16/2022 | JOSEPH RAFOLS |
| Issued | 12/1/2022 | APPLICANT |
| CofO in Progress | 5/25/2023 | JEFFREY BULL |
| Permit Finaled | 5/25/2023 | JOHN JANSON |
| CofO Issued | 5/25/2023 | JOHN JANSON |
| Permit Finaled | 5/25/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/8/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/8/2022 | DAGOVERTO GUERRERO |
| ZI | Cleared | 9/15/2022 | STEVEN WECHSLER |
| Low Impact Development | Cleared | 11/8/2022 | CHRIS VONG |
| Construction within easement | Cleared | 11/9/2022 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 11/15/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 11/15/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 11/15/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 11/15/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Santos,, Michael; Lic. No.: C77657 | 16202 ORION AVE CHINO, CA 91708 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/14/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 12/14/2022 | Corrections Issued | DAVID SANDOVAL |
| Sewer | 12/14/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 12/20/2022 | Not Ready for Inspection | JEFFREY BULL |
| Sewer | 12/20/2022 | Partial Approval | JEFFREY BULL |
| Underground Mechanical | 12/20/2022 | Approved | JEFFREY BULL |
| Excavation/Setback/Form/Re-Bar | 12/23/2022 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 12/23/2022 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 1/12/2023 | Not Ready for Inspection | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2023 | Partial Approval | JEFFREY PARD |
| Verify Sprinkler Sign Off | 1/12/2023 | Not Ready for Inspection | JEFFREY PARD |
| Interior/Exterior Lathing | 1/17/2023 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Rough | 1/25/2023 | Approved | JEFFREY BULL |
| Gas Test | 1/25/2023 | Not Ready for Inspection | JEFFREY BULL |
| Interior/Exterior Lathing | 1/25/2023 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Rough | 1/25/2023 | Not Ready for Inspection | JEFFREY BULL |
| BUILDING-Rough-Frame | 1/26/2023 | Approved | JEFFREY BULL |
| Gas Test | 1/26/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 1/26/2023 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 1/26/2023 | Approved | JEFFREY BULL |
| Verify Sprinkler Sign Off | 1/26/2023 | Approved | JEFFREY BULL |
| Insulation | 2/9/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 2/13/2023 | No Access for Inspection | KRISTEN CAUSEY |
| Drywall Nailing | 2/16/2023 | Approved | JESUS PINEDA |
| Underground Mechanical | 2/16/2023 | Approved | JESUS PINEDA |
| Final | 4/12/2023 | Corrections Issued | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 4/12/2023 | SGSOV Not Ready | JEFFREY BULL |
| Service/Power Release | 4/12/2023 | Not Ready for Inspection | JEFFREY BULL |
| Smoke Detectors | 4/12/2023 | Approved | JEFFREY BULL |
| Final | 5/25/2023 | OK to Issue CofO | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 5/25/2023 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 5/25/2023 | Approved | JEFFREY BULL |