7034 1/2 N YOLANDA AVE 91335
Certificate Information: 7034 1/2 N YOLANDA AVE 91335
- Application / Permit
- 22010-20000-03979
- Plan Check / Job No.
- B22VN12239
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN. (N) SINGLE FAMILY DWELLING PER SB9 TWO-UNIT DEVELOPMENT CA GOVT CODE 65852.21
- Permit Issued
- Issued on 6/25/2024
- Issuing Office
- Current Status
- CofO Issued on 6/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | LAMAR DAVIS |
| Corrections Issued | 8/19/2022 | LAMAR DAVIS |
| Quality Review Completed | 8/31/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 12/2/2022 | LAMAR DAVIS |
| Plan Check Approved | 2/7/2023 | ARSALAN SHABESTARI |
| Issued | 6/25/2024 | APPLICANT |
| CofO in Progress | 1/15/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 6/16/2025 | JOHN JANSON |
| CofO Issued | 6/16/2025 | JOHN JANSON |
| Permit Finaled | 6/16/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/6/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 10/8/2022 | RUEL COLE |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/17/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 10/31/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 10/31/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 10/31/2022 | JOSE DUARTE-DIAZ |
| Senate Bill 9 | Cleared | 11/23/2022 | ASHLEY RODARTE |
| ZI | Cleared | 11/23/2022 | ASHLEY RODARTE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gosen,, James W; Lic. No.: NA43590 | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/28/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 6/28/2024 | Partial Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2024 | Partial Approval | JEFFREY BULL |
| Special/Order Compliance | 7/8/2024 | Corrections Issued | JEFFREY BULL |
| Deputy Wood Construction | 7/15/2024 | Conditional Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 7/19/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 7/19/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 8/1/2024 | Partial Approval | JEFFREY BULL |
| Green Building Rough | 8/1/2024 | Approved | JEFFREY BULL |
| HVAC-Rough | 8/1/2024 | Approved | JEFFREY BULL |
| Insulation | 8/7/2024 | Corrections Issued | JEFFREY BULL |
| Interior/Exterior Lathing | 8/7/2024 | Partial Approval | JEFFREY BULL |
| Drywall Nailing | 8/19/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 8/19/2024 | Approved | JEFFREY BULL |
| Underground Mechanical | 9/10/2024 | Partial Approval | JEFFREY BULL |
| BUILDING-Rough-Frame | 1/7/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 1/7/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 1/7/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 1/7/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 1/7/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Final | 1/7/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 1/7/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 1/7/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 1/7/2025 | Approved | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 1/7/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 1/14/2025 | Approved | ARUTYUN MADATYAN |
| Final | 1/14/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 1/14/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 1/14/2025 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 1/14/2025 | Approved | ARUTYUN MADATYAN |
| Special/Order Compliance | 2/21/2025 | Corrections Issued | ARUTYUN MADATYAN |