12942 W OBERLIN ST 91342

Certificate Information: 12942 W OBERLIN ST 91342

Application / Permit
22010-20000-03974
Plan Check / Job No.
B22VN12224
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN New detached ADU per LAMC 12.22 A.33(c) and (d) “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 12/20/2022
Issuing Office
Current Status
CofO Issued on 5/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2022 APPLICANT
Assigned to Plan Check Engineer 8/15/2022 LUKE GONZALES
Corrections Issued 8/16/2022 LUKE GONZALES
Applicant returned to address corrections 10/29/2022 SAMUEL GONZALEZ
Plan Check Approved 12/14/2022 LUKE GONZALES
Issued 12/20/2022 APPLICANT
CofO in Progress 5/10/2024 KEVIN BERBERYAN
Permit Finaled 5/15/2024 RUBEN SALAS
CofO Issued 5/15/2024 RUBEN SALAS
Permit Finaled 5/15/2024 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 9/29/2022 WALTER RAMIREZ
Address approval Cleared 10/4/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 10/6/2022 SERGIO VALENZUELA
Roof/Waste drainage to street Cleared 10/25/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 10/27/2022 COLIN LOREDO
Sewer availability Cleared 10/27/2022 COLIN LOREDO
GPI Written Notices Cleared 12/13/2022 LUKE GONZALES

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/2/2023 Partial Inspection ARAM AVEDISIAN
PLUMBING-Rough 2/6/2023 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 2/13/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 2/16/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/22/2023 Partial Approval ARAM AVEDISIAN
Deputy Wood Construction 3/30/2023 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 4/10/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 4/10/2023 Approved ARAM AVEDISIAN
Green Building Rough 4/10/2023 Conditional Approval ARAM AVEDISIAN
HVAC-Rough 4/10/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 4/10/2023 Approved ARAM AVEDISIAN
Insulation 4/14/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 4/14/2023 Partial Approval ARAM AVEDISIAN
Shower Pan 4/14/2023 Approved ARAM AVEDISIAN
Drywall Nailing 4/18/2023 Approved ARAM AVEDISIAN
Green Building Rough 4/18/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 5/15/2023 Partial Approval ARAM AVEDISIAN
Gas Test 7/7/2023 Approved ROBERT GOLD
Underground Mechanical 7/7/2023 Partial Approval ROBERT GOLD
Sewer 7/19/2023 Approved DAVID ANDERSON
Underground Mechanical 7/19/2023 Partial Approval DAVID ANDERSON
ELECTRICAL-Final 8/29/2023 Not Ready for Inspection KEVIN BERBERYAN
Final 8/29/2023 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 8/29/2023 Approved KEVIN BERBERYAN
Green Building Final 8/29/2023 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Final 8/29/2023 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Final 8/29/2023 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 8/29/2023 SGSOV Not Ready KEVIN BERBERYAN
Service/Power Release 8/29/2023 Not Ready for Inspection KEVIN BERBERYAN
Smoke Detectors 8/29/2023 Approved KEVIN BERBERYAN
Final 9/6/2023 Corrections Issued KEVIN BERBERYAN
Green Building Final 9/6/2023 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/6/2023 SGSOV Approved KEVIN BERBERYAN
Service/Power Release 9/6/2023 Corrections Issued KEVIN BERBERYAN
Service/Power Release 10/16/2023 Approved KEVIN BERBERYAN
Final 1/31/2024 Corrections Issued ROBERT GOLD
ELECTRICAL-Final 5/9/2024 Approved KEVIN BERBERYAN
Final 5/9/2024 OK to Issue CofO KEVIN BERBERYAN