7733 N ALDEA AVE 91406
Certificate Information: 7733 N ALDEA AVE 91406
- Application / Permit
- 22010-20000-03926
- Plan Check / Job No.
- B22VN12041
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 31' X 45' IRREG SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 9/21/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 8/9/2022 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 8/11/2022 | APPLICANT |
| Plan Check Approved | 9/21/2022 | JEROME MAGAT PALMA |
| Issued | 9/21/2022 | APPLICANT |
| CofO in Progress | 10/24/2024 | RAUL OLAGI |
| Permit Finaled | 10/28/2024 | DANIEL ORRANTE |
| CofO Issued | 10/28/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/28/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/15/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 8/16/2022 | COLIN LOREDO |
| Construction near power lines | Cleared | 8/23/2022 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 9/15/2022 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 9/19/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/24/2023 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 2/21/2023 | Not Ready for Inspection | RAUL OLAGI |
| Underground Mechanical | 2/21/2023 | Corrections Issued | RAUL OLAGI |
| Underground Mechanical | 2/23/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 3/3/2023 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 3/9/2023 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2023 | Corrections Issued | RAUL OLAGI |
| Deputy Drilled-In Anchors | 5/10/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2023 | Approved | RAUL OLAGI |
| Sewer | 7/3/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 7/3/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 8/11/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 8/11/2023 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 8/11/2023 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 8/11/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/8/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/8/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 9/8/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 9/8/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 9/8/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 9/8/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/12/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 9/12/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 9/12/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 9/12/2023 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 9/12/2023 | Approved | RAUL OLAGI |
| Insulation | 9/18/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Drywall Nailing | 10/2/2023 | Approved | RAUL OLAGI |
| Shower Pan | 12/5/2023 | Corrections Issued | RAUL OLAGI |
| Shower Pan | 12/12/2023 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 12/19/2023 | Approved | RAUL OLAGI |
| Shower Pan | 12/19/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 7/8/2024 | Corrections Issued | RAUL OLAGI |
| Final | 7/8/2024 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 7/8/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 7/8/2024 | Corrections Issued | RAUL OLAGI |
| Final | 7/17/2024 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 7/17/2024 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 7/17/2024 | SGSOV Approved | RAUL OLAGI |
| Service/Power Release | 7/17/2024 | Not Ready for Inspection | RAUL OLAGI |
| Smoke Detectors | 7/17/2024 | Approved | RAUL OLAGI |
| Final | 7/29/2024 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 7/29/2024 | Approved | RAUL OLAGI |
| Final | 8/8/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Service/Power Release | 8/8/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 9/3/2024 | Approved | RAUL OLAGI |
| Final | 9/3/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 9/3/2024 | Approved | RAUL OLAGI |
| Service/Power Release | 9/3/2024 | Not Ready for Inspection | RAUL OLAGI |
| Final | 10/24/2024 | OK to Issue CofO | RAUL OLAGI |
| Service/Power Release | 10/24/2024 | Approved | RAUL OLAGI |