20441 W ROBERT PL 91364
Certificate Information: 20441 W ROBERT PL 91364
- Application / Permit
- 22010-20000-03925
- Plan Check / Job No.
- B22VN12037
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- (N) 13'11-1/2" X 16'4-1/2" DETACHED PATIO COVER, TYPE V-A, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 12/19/2022
- Issuing Office
- Current Status
- CofO Issued on 8/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | RARES BODEA |
| Corrections Issued | 8/22/2022 | RARES BODEA |
| Quality Review Completed | 8/25/2022 | STEVEN KIM |
| Building Plans Picked Up | 8/30/2022 | APPLICANT |
| Applicant returned to address corrections | 9/28/2022 | RARES BODEA |
| Applicant returned to address corrections | 12/9/2022 | RARES BODEA |
| Plan Check Approved | 12/19/2022 | RARES BODEA |
| Issued | 12/19/2022 | APPLICANT |
| CofO in Progress | 6/17/2024 | JOHN HAYES |
| Permit Finaled | 8/2/2024 | JOHN JANSON |
| CofO Issued | 8/2/2024 | JOHN JANSON |
| Permit Finaled | 8/2/2024 | JOHN JANSON |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/23/2022 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/23/2022 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/23/2022 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/23/2022 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/23/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/23/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 9/9/2022 | SUNG JOON WON |
| Hydrant and Access approval | Cleared | 9/12/2022 | MATTHEW CRAIG |
| Distance to fire station | Cleared | 9/15/2022 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 9/20/2022 | DAGOVERTO GUERRERO |
| GPI Written Notices | Cleared | 9/28/2022 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 9/28/2022 | RARES BODEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mirzadeh,, Amir; Lic. No.: C58119 | P O BOX 572110 TARZANA, CA 91357 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
| Geologist | Rahimikian,, Pedram; Lic. No.: EG2683 | 21414 ARCOS DRIVE WOODLAND HILLS, CA 91364 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/3/2023 | Corrections Issued | PETER FOLLING |
| Excavation/Setback/Form/Re-Bar | 3/6/2023 | Partial Approval | PETER FOLLING |
| Footing/Foundation/Slab | 3/30/2023 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2023 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 5/19/2023 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 7/24/2023 | Approved | PETER FOLLING |
| Green Building Rough | 7/24/2023 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 7/24/2023 | Approved | PETER FOLLING |
| Verify Sprinkler Sign Off | 7/24/2023 | Approved | PETER FOLLING |
| ELECTRICAL-Final | 1/26/2024 | Approved | JOHN KIDWELL |
| Drywall Nailing | 5/31/2024 | Not Ready for Inspection | JOHN HAYES |
| Final | 5/31/2024 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 5/31/2024 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Approved | JOHN HAYES |
| Service/Power Release | 5/31/2024 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 5/31/2024 | Approved | JOHN HAYES |
| Drywall Nailing | 6/13/2024 | Approved | JOHN HAYES |
| Final | 6/13/2024 | OK to Issue CofO | JOHN HAYES |
| Service/Power Release | 6/13/2024 | Approved | JOHN HAYES |