7807 W APPERSON ST 91040
Certificate Information: 7807 W APPERSON ST 91040
- Application / Permit
- 22010-20000-03916
- Plan Check / Job No.
- B22VN12015
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: EGRESS AND INGRESS ADDITION AND CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/24/2022
- Issuing Office
- Current Status
- CofO Issued on 11/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2022 | DANIEL YIP |
| Corrections Issued | 8/15/2022 | DANIEL YIP |
| Applicant returned to address corrections | 9/16/2022 | DANIEL YIP |
| Applicant returned to address corrections | 10/12/2022 | DANIEL YIP |
| Plan Check Approved | 10/23/2022 | DANIEL YIP |
| Issued | 10/24/2022 | APPLICANT |
| CofO in Progress | 9/13/2023 | DAVID ANDERSON |
| Permit Finaled | 11/9/2023 | RUBEN SALAS |
| CofO Issued | 11/9/2023 | RUBEN SALAS |
| Permit Finaled | 11/9/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/5/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 10/5/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 10/5/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2022 | ROMAN GUTIERREZ |
| Specific Plan | Cleared | 10/19/2022 | SARAH HOUNSELL |
| Grading Pre-Inspection | Cleared | 10/20/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/27/2023 | Approved | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 5/12/2023 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 5/12/2023 | Partial Approval | DAVID ANDERSON |
| Sewer | 5/12/2023 | Approved | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 5/15/2023 | Conditional Approval | MICHAEL SMITH |
| Excavation/Setback/Form/Re-Bar | 5/19/2023 | Corrections Issued | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 5/30/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 6/26/2023 | Approved | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 7/3/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/14/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 7/14/2023 | Approved | DAVID ANDERSON |
| Insulation | 7/14/2023 | Corrections Issued | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/14/2023 | Approved | DAVID ANDERSON |
| Insulation | 7/17/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 7/21/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/1/2023 | Approved | WILLIAM WREN |
| Shower Pan | 8/1/2023 | Approved | WILLIAM WREN |
| Final | 9/8/2023 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 9/8/2023 | Approved | DAVID ANDERSON |
| Green Building Final | 9/8/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 9/8/2023 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 9/8/2023 | Approved | DAVID ANDERSON |
| Final | 9/12/2023 | OK to Issue CofO | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 9/12/2023 | SGSOV Approved | DAVID ANDERSON |