13844 W HAMLIN ST 91401

Certificate Information: 13844 W HAMLIN ST 91401

Application / Permit
22010-20000-03910
Plan Check / Job No.
B22VN11994
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d) WITH SIDE AND REAR PATIO COVERS. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.”
Permit Issued
Issued on 2/23/2023
Issuing Office
Current Status
CofO Issued on 1/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2022 APPLICANT
Assigned to Plan Check Engineer 8/11/2022 KEVIN MORALES
Corrections Issued 8/11/2022 KEVIN MORALES
Applicant returned to address corrections 9/7/2022 KEVIN MORALES
Applicant returned to address corrections 9/28/2022 KEVIN MORALES
Applicant returned to address corrections 1/17/2023 ARSALAN SHABESTARI
Applicant returned to address corrections 1/19/2023 ADAM HEGAZI
Plan Check Approved 2/1/2023 ADAM HEGAZI
Issued 2/23/2023 APPLICANT
CofO in Progress 11/14/2025 RYAN SALAZAR
Permit Finaled 1/8/2026 RUBEN SALAS
CofO Issued 1/8/2026 RUBEN SALAS
Permit Finaled 1/8/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/19/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 8/25/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 8/30/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 8/30/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 8/30/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Kyupelyan,, Emil; Lic. No.: C91238 8045 LASAINE AVE      NORTHRIDGE, CA 91325

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/22/2023 Partial Approval RYAN SALAZAR
Deputy Drilled-In Anchors 10/13/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/21/2023 Partial Approval RYAN SALAZAR
Drywall Nailing 3/24/2025 Approved RYAN SALAZAR
Final 3/24/2025 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 3/24/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 3/24/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 3/24/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 3/24/2025 Approved RYAN SALAZAR
Wood Frame 3/24/2025 Approved RYAN SALAZAR
Final 9/19/2025 Partial Inspection RYAN SALAZAR