8434 N GOTHIC AVE 91343

Certificate Information: 8434 N GOTHIC AVE 91343

Application / Permit
22010-20000-03908
Plan Check / Job No.
B22VN11992
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 10/27/2024
Issuing Office
Current Status
CofO Issued on 4/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/8/2022 APPLICANT
Assigned to Plan Check Engineer 8/26/2022 DANIEL YIP
Corrections Issued 8/29/2022 DANIEL YIP
Quality Review Completed 8/31/2022 GARO TELMI
Applicant returned to address corrections 9/10/2024 DANIEL YIP
Plan Check Approved 10/21/2024 DANIEL YIP
Issued 10/27/2024 APPLICANT
CofO in Progress 3/17/2026 GAREN HAYRAPETYAN
CofO in Progress 4/4/2026 RAUL OLAGI
CofO Issued 4/15/2026 RUBEN SALAS
Permit Finaled 4/15/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/19/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 4/1/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 4/29/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/8/2024 CARLOS AGUILERA
Private sewage disp. approval Cleared 9/11/2024 DAN RYAN EVANGELISTA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/7/2025 Conditional Approval SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 1/17/2025 Approved GAREN HAYRAPETYAN
Footing/Foundation/Slab 1/17/2025 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 1/31/2025 Partial Approval SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 2/10/2025 Partial Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 2/11/2025 Approved GAREN HAYRAPETYAN
Deputy Wood Construction 2/12/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 4/18/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 4/18/2025 Partial Approval NICHOLAS TROWBRIDGE
Green Building Rough 4/18/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
HVAC-Rough 4/18/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Rough 4/18/2025 Approved NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 4/18/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 4/23/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 4/23/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 4/23/2025 Approved GAREN HAYRAPETYAN
Sewer 4/23/2025 Approved GAREN HAYRAPETYAN
Insulation 4/29/2025 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 4/29/2025 Partial Approval SALVADOR MARTINEZ
Shower Pan 4/29/2025 Approved SALVADOR MARTINEZ
Insulation 5/12/2025 No Access for Inspection SALVADOR MARTINEZ
Interior/Exterior Lathing 5/12/2025 No Access for Inspection SALVADOR MARTINEZ
Insulation 5/13/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 5/13/2025 Approved GAREN HAYRAPETYAN
Drywall Nailing 5/15/2025 Not Ready for Inspection MICHAEL CORTEZ
Green Building Rough 5/15/2025 Not Ready for Inspection MICHAEL CORTEZ
Drywall Nailing 5/19/2025 Approved MICHAEL CORTEZ
Green Building Rough 5/19/2025 Approved MICHAEL CORTEZ
Excavation/Setback/Form/Re-Bar 5/23/2025 Partial Inspection GAREN HAYRAPETYAN
ELECTRICAL-Final 12/8/2025 No Access for Inspection GAREN HAYRAPETYAN
HVAC-Final 12/8/2025 No Access for Inspection GAREN HAYRAPETYAN
PLUMBING-Final 12/8/2025 No Access for Inspection GAREN HAYRAPETYAN
HVAC-Final 1/13/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Final 1/13/2026 Approved GAREN HAYRAPETYAN
Underground Mechanical 1/13/2026 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 1/27/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Final 1/27/2026 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 1/27/2026 Approved GAREN HAYRAPETYAN
HVAC-Final 1/27/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Final 1/27/2026 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 1/27/2026 SGSOV No Gas GAREN HAYRAPETYAN
Service/Power Release 1/27/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Smoke Detectors 1/27/2026 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 3/17/2026 Approved GAREN HAYRAPETYAN
Final 3/17/2026 OK to Issue CofO GAREN HAYRAPETYAN
Service/Power Release 3/17/2026 Approved GAREN HAYRAPETYAN