6336 N CAMELLIA AVE 91606
Certificate Information: 6336 N CAMELLIA AVE 91606
- Application / Permit
- 22010-20000-03903
- Plan Check / Job No.
- B22VN11985
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan 1190 SF DETACHED ADU PER LAMC 12.22 A 33(C) and (d)
- Permit Issued
- Issued on 4/27/2023
- Issuing Office
- Current Status
- CofO Issued on 11/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | VARAND SARKISIAN |
| Corrections Issued | 8/30/2022 | VARAND SARKISIAN |
| Quality Review Completed | 9/4/2022 | PRANITA SHAH |
| Plan Check Approved | 4/27/2023 | VARAND SARKISIAN |
| Issued | 4/27/2023 | APPLICANT |
| CofO in Progress | 10/3/2024 | ROBERTO PALACIOS-LOPEZ |
| No Progress | 11/14/2024 | ROBERTO PALACIOS-LOPEZ |
| CofO in Progress | 11/14/2024 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 11/15/2024 | DANIEL ORRANTE |
| CofO Issued | 11/15/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/15/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/6/2023 | MITESH PATEL |
| Construction near power lines | Cleared | 3/9/2023 | WALTER RAMIREZ |
| Address approval | Cleared | 3/31/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2023 | FERNANDO GIL |
| Sewer availability | Cleared | 4/3/2023 | FERNANDO GIL |
| Roof/Waste drainage to street | Cleared | 4/6/2023 | FERNANDO GIL |
Contact Information
| Contractor | Pure Energy Solutions Inc; Lic. No.: 1076924-B | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/22/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 6/22/2023 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/23/2023 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2023 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2023 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2023 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2023 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2023 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2023 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/20/2023 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Rough | 11/20/2023 | Partial Approval | DAVID MATSON |
| HVAC-Rough | 11/20/2023 | Not Ready for Inspection | DAVID MATSON |
| PLUMBING-Rough | 11/20/2023 | Not Ready for Inspection | DAVID MATSON |
| Verify Sprinkler Sign Off | 11/20/2023 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 11/27/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Gas Test | 11/27/2023 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 11/27/2023 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 11/27/2023 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/4/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/8/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/14/2023 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 12/18/2023 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 12/22/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 12/29/2023 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 1/5/2024 | Approved | RYAN SALAZAR |
| Insulation | 1/9/2024 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 1/18/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 1/24/2024 | Corrections Issued | JOHN COLEMAN |
| Interior/Exterior Lathing | 1/31/2024 | Approved | JENNIFER RABUCHIN |
| Final | 5/22/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/22/2024 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 5/22/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 5/22/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 5/22/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 8/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/9/2024 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 8/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 8/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 9/26/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/26/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 9/26/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 10/1/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 10/1/2024 | Approved | ROBERTO PALACIOS-LOPEZ |