4730 N COLUMBUS AVE 91403
Certificate Information: 4730 N COLUMBUS AVE 91403
- Application / Permit
- 22010-20000-03890
- Plan Check / Job No.
- B22VN11951
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 11/4/2022
- Issuing Office
- Current Status
- CofO Issued on 9/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 8/23/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 8/30/2022 | STEVEN KIM |
| Building Plans Picked Up | 8/30/2022 | APPLICANT |
| Applicant returned to address corrections | 9/23/2022 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 10/21/2022 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 11/1/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 11/3/2022 | NILOOFAR MEHRAIN |
| Issued | 11/4/2022 | APPLICANT |
| CofO in Progress | 8/10/2023 | THOMAS FINNILA |
| CofO in Progress | 8/10/2023 | THOMAS FINNILA |
| Permit Finaled | 9/18/2023 | RUBEN SALAS |
| CofO Issued | 9/18/2023 | RUBEN SALAS |
| Permit Finaled | 9/18/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/24/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 8/24/2022 | COLIN LOREDO |
| Low Impact Development | Cleared | 9/23/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 9/23/2022 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 9/30/2022 | KURT CORRAL |
Contact Information
| Contractor | Nork Construction Inc; Lic. No.: 1058592-B | 17204 CHATSWORTH ST #10 GRANADA HILLS, CA 91344 |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/23/2022 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 11/30/2022 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 12/1/2022 | Approved | THOMAS FINNILA |
| Deputy Reinf. Concrete | 12/5/2022 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2022 | Corrections Issued | JOHN COLEMAN |
| Deputy Wood Construction | 12/12/2022 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 12/29/2022 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 12/29/2022 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 1/10/2023 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Rough | 1/10/2023 | Approved | JOHN COLEMAN |
| Green Building Rough | 1/10/2023 | Approved | JOHN COLEMAN |
| MERV13>=Rough | 1/10/2023 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 1/10/2023 | Approved | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 1/10/2023 | Not Ready for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 1/17/2023 | Partial Approval | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 1/17/2023 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 1/23/2023 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 1/24/2023 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 1/27/2023 | Approved | THOMAS FINNILA |
| Insulation | 1/31/2023 | Conditional Approval | MISAEL ESPARZA |
| Drywall Nailing | 2/3/2023 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 2/16/2023 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 2/27/2023 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 6/27/2023 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 6/27/2023 | Approved | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/25/2023 | Approved | THOMAS FINNILA |
| HVAC-Final | 7/25/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 7/31/2023 | OK to Issue CofO | THOMAS FINNILA |
| Green Building Final | 7/31/2023 | Approved | THOMAS FINNILA |
| HVAC-Final | 7/31/2023 | Approved | THOMAS FINNILA |
| MERV13>=Final | 7/31/2023 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/31/2023 | SGSOV Approved | THOMAS FINNILA |
| Service/Power Release | 7/31/2023 | Approved | THOMAS FINNILA |
| Smoke Detectors | 7/31/2023 | Approved | THOMAS FINNILA |