6330 N CAMELLIA AVE 91606
Certificate Information: 6330 N CAMELLIA AVE 91606
- Application / Permit
- 22010-20000-03880
- Plan Check / Job No.
- B22VN11921
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACH 2 STORY (36'-6"x21'-0"), 1200 SQFT ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 5/2/2023
- Issuing Office
- Current Status
- CofO Issued on 9/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | PETER MOSESIAN |
| Corrections Issued | 8/31/2022 | PETER MOSESIAN |
| Quality Review Completed | 9/7/2022 | OMID HEDAYAT |
| Plan Check Approved | 5/2/2023 | PETER MOSESIAN |
| Issued | 5/2/2023 | APPLICANT |
| CofO in Progress | 8/2/2024 | JOSE AVILA |
| Permit Finaled | 9/10/2024 | DANIEL ORRANTE |
| CofO Issued | 9/10/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/10/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/27/2023 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 3/30/2023 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 3/30/2023 | LUIS LUVANO |
| Address approval | Cleared | 3/31/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2023 | FERNANDO GIL |
| Sewer availability | Cleared | 3/31/2023 | FERNANDO GIL |
| Roof/Waste drainage to street | Cleared | 4/6/2023 | FERNANDO GIL |
Contact Information
| Contractor | Pure Energy Solutions Inc; Lic. No.: 1076924-B | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/22/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 6/22/2023 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/23/2023 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2023 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2023 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2023 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2023 | Partial Approval | JENNIFER RABUCHIN |
| Special/Order Compliance | 8/29/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/5/2023 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 9/6/2023 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 9/6/2023 | Approved | CHRISTOPHE COCHRAN |
| Rough-Elec/Plmb/HVAC | 10/2/2023 | Corrections Issued | JOHN HAYES |
| HVAC-Rough | 10/17/2023 | Approved | JOHN HAYES |
| Wood Frame | 10/23/2023 | Corrections Issued | MISAEL ESPARZA |
| Wood Frame | 10/25/2023 | Approved | MICHEL ABAJAN |
| Wood Frame | 10/30/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Insulation | 11/8/2023 | Corrections Issued | JOHN HAYES |
| Interior/Exterior Lathing | 11/8/2023 | Partial Approval | JOHN HAYES |
| Insulation | 11/15/2023 | Approved | JOHN HAYES |
| Drywall Nailing | 11/29/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 11/29/2023 | Not Ready for Inspection | JOHN HAYES |
| Shower Pan | 12/13/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 12/15/2023 | Corrections Issued | JOHN HAYES |
| Interior/Exterior Lathing | 12/20/2023 | Partial Approval | JOHN HAYES |
| Shower Pan | 12/20/2023 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 12/22/2023 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 2/6/2024 | Approved | JOHN HAYES |
| Final | 2/6/2024 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/6/2024 | SGSOV Approved | JOHN HAYES |
| Service/Power Release | 2/6/2024 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 2/6/2024 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 2/6/2024 | Approved | JOHN HAYES |
| Final | 4/1/2024 | Corrections Issued | JOHN HAYES |
| Service/Power Release | 4/1/2024 | Not Ready for Inspection | JOHN HAYES |
| Final | 5/30/2024 | Corrections Issued | JOSE AVILA |
| Service/Power Release | 5/30/2024 | Not Ready for Inspection | JOSE AVILA |
| Final | 7/25/2024 | Not Required | JOSE AVILA |
| Final | 8/1/2024 | OK to Issue CofO | JOSE AVILA |
| Service/Power Release | 8/1/2024 | Approved | JOSE AVILA |