11055 W KITTRIDGE ST 91606
Certificate Information: 11055 W KITTRIDGE ST 91606
- Application / Permit
- 22010-20000-03860
- Plan Check / Job No.
- B22VN11840
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* NEW 30'-2" X 25'-4" TWO STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 5/1/2023
- Issuing Office
- Current Status
- CofO Issued on 12/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2022 | SELLA BENYAMIN |
| Corrections Issued | 8/29/2022 | SELLA BENYAMIN |
| Quality Review Completed | 9/1/2022 | STEVEN KIM |
| Plan Check Approved | 4/25/2023 | SELLA BENYAMIN |
| Issued | 5/1/2023 | APPLICANT |
| CofO in Progress | 11/13/2024 | JOSE AVILA |
| Permit Finaled | 12/4/2024 | RUBEN SALAS |
| CofO Issued | 12/4/2024 | RUBEN SALAS |
| Permit Finaled | 12/4/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/7/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 9/8/2022 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 1/4/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 1/6/2023 | ROMAN GUTIERREZ |
| Construction near power lines | Cleared | 3/8/2023 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/25/2023 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/31/2023 | Approved | JOHN HAYES |
| Underground Mechanical | 7/31/2023 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 8/7/2023 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 8/18/2023 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 11/20/2023 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Rough | 11/20/2023 | Not Ready for Inspection | DAVID MATSON |
| HVAC-Rough | 11/20/2023 | Not Ready for Inspection | DAVID MATSON |
| PLUMBING-Rough | 11/20/2023 | Not Ready for Inspection | DAVID MATSON |
| Verify Sprinkler Sign Off | 11/20/2023 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Rough | 11/21/2023 | Partial Approval | ROBERT GOLD |
| HVAC-Rough | 11/21/2023 | Approved | ROBERT GOLD |
| PLUMBING-Rough | 11/21/2023 | Partial Approval | ROBERT GOLD |
| Deputy Wood Construction | 11/28/2023 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 1/23/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 1/23/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 1/23/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 1/23/2024 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 1/23/2024 | Approved | RYAN SALAZAR |
| Wood Frame | 1/23/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 1/31/2024 | Partial Approval | RYAN SALAZAR |
| Insulation | 2/7/2024 | Approved | JOHN HAYES |
| Drywall Nailing | 3/26/2024 | Approved | KEVIN BERBERYAN |
| Sewer | 3/26/2024 | Approved | KEVIN BERBERYAN |
| Shower Pan | 3/26/2024 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 3/26/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 4/8/2024 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 7/8/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Final | 8/28/2024 | Corrections Issued | JOSE AVILA |
| Final | 9/25/2024 | Not Ready for Inspection | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 9/25/2024 | SGSOV Not Ready | JOSE AVILA |
| Smoke Detectors | 9/25/2024 | Approved | JOSE AVILA |
| Final | 10/17/2024 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 10/17/2024 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 10/17/2024 | Not Ready for Inspection | JOSE AVILA |
| Final | 11/12/2024 | OK to Issue CofO | JOSE AVILA |
| Service/Power Release | 11/12/2024 | Approved | JOSE AVILA |