13793 N BORDEN AVE 91342
Certificate Information: 13793 N BORDEN AVE 91342
- Application / Permit
- 22010-20000-03819
- Plan Check / Job No.
- B22VN11708
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan NEW 34' X 43'-9" IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/17/2023
- Issuing Office
- Current Status
- CofO Issued on 4/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | RAPHAEL ROSAS |
| Corrections Issued | 8/31/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 9/1/2022 | STEVEN KIM |
| Applicant returned to address corrections | 6/23/2023 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 7/5/2023 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 7/11/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 8/4/2023 | RAPHAEL ROSAS |
| Issued | 8/17/2023 | APPLICANT |
| CofO in Progress | 4/9/2024 | KEVIN BERBERYAN |
| Permit Finaled | 4/11/2024 | RUBEN SALAS |
| CofO Issued | 4/11/2024 | RUBEN SALAS |
| Permit Finaled | 4/11/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/27/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/28/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 6/14/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 7/6/2023 | ROMAN GUTIERREZ |
| Tract Map conditions | Cleared | 7/13/2023 | BRENNEN OBETO |
| ZA Case | Cleared | 7/13/2023 | BRENNEN OBETO |
| Hydrant and Access approval | Cleared | 7/28/2023 | LAVEON RIDER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/13/2023 | Corrections Issued | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 9/13/2023 | Partial Inspection | KEVIN BERBERYAN |
| Pre-Inspection | 9/13/2023 | Corrections Issued | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 9/18/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Underground Mechanical | 9/18/2023 | Approved | KEVIN BERBERYAN |
| Deputy Reinf. Concrete | 9/21/2023 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 9/21/2023 | Approved | KEVIN BERBERYAN |
| Pre-Inspection | 9/21/2023 | Partial Inspection | KEVIN BERBERYAN |
| Deputy Wood Construction | 10/18/2023 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 10/20/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Rough | 10/20/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| MERV13>=Rough | 10/20/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 10/20/2023 | Partial Inspection | KEVIN BERBERYAN |
| Wood Frame | 10/20/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 11/1/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 11/1/2023 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 11/1/2023 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 11/1/2023 | Approved | KEVIN BERBERYAN |
| MERV13>=Rough | 11/1/2023 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 11/1/2023 | Approved | KEVIN BERBERYAN |
| Sewer | 11/1/2023 | Approved | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 11/1/2023 | Approved | KEVIN BERBERYAN |
| Wood Frame | 11/1/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 11/14/2023 | Approved | KEVIN BERBERYAN |
| Insulation | 11/14/2023 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/21/2023 | Approved | KEVIN BERBERYAN |
| Shower Pan | 11/21/2023 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 11/30/2023 | Conditional Approval | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/30/2023 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 12/7/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 3/22/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 3/22/2024 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 3/22/2024 | Approved | KEVIN BERBERYAN |
| Green Building Final | 3/22/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Final | 3/22/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| MERV13>=Final | 3/22/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 3/22/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 3/22/2024 | SGSOV Not Ready | KEVIN BERBERYAN |
| Service/Power Release | 3/22/2024 | Not Required | KEVIN BERBERYAN |
| Smoke Detectors | 3/22/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 3/27/2024 | Approved | KEVIN BERBERYAN |
| Final | 3/27/2024 | OK to Issue CofO | KEVIN BERBERYAN |
| HVAC-Final | 3/27/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 3/27/2024 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 3/27/2024 | SGSOV Approved | KEVIN BERBERYAN |